19339 W VICTORY BLVD 102 91335
Certificate Information: 19339 W VICTORY BLVD 102 91335
- Application / Permit
- 24016-20000-09128
- Plan Check / Job No.
- B24VN03595
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- ePlan. CHANGE OF USE FORM OFFICE TO DENTAL OFFICE. NON STRUCTURAL PARTITIONS, TWO RESTROOMS, MECHANICAL DISTRIBUTION SUPPLY/RETURNS, T-BAR CEILING, LIGHTS, OUTLETS, SWITCHES: LIMIT THE HOURS OF OPERATION FROM 7am TO 11pm.
- Permit Issued
- Issued on 11/26/2025
- Issuing Office
- Current Status
- CofO Issued on 7/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | AUNG SOE |
| Corrections Issued | 3/26/2024 | AUNG SOE |
| Applicant returned to address corrections | 5/25/2024 | AUNG SOE |
| Plan Check Approved | 5/27/2024 | AUNG SOE |
| Issued | 11/26/2025 | APPLICANT |
| CofO in Progress | 6/29/2026 | BRIAN KELLY |
| Permit Finaled | 7/1/2026 | RICKEY JACKSON |
| CofO Issued | 7/1/2026 | RICKEY JACKSON |
| Permit Finaled | 7/1/2026 | RICKEY JACKSON |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 5/21/2024 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/21/2024 | CARLOS AGUILERA |
| ZA Case | Cleared | 5/21/2024 | YINGSHI HUANG |
| ZA Case | Cleared | 5/21/2024 | YINGSHI HUANG |
| ZA Case | Cleared | 5/21/2024 | YINGSHI HUANG |
| ZA Case | Cleared | 5/21/2024 | YINGSHI HUANG |
| ZI | Cleared | 5/21/2024 | YINGSHI HUANG |
Contact Information
| Architect | Webb,, Brandon Brian; Lic. No.: C39403 | 2936 CIMARRON RD RIVERSIDE, CA 92506 |
| Contractor | Donald Webb; Lic. No.: 709664-B | , |
| Contractor | Webb Donald B; Lic. No.: 709664-B | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/18/2026 | Approved | BRIAN KELLY |
| Drywall Nailing | 2/23/2026 | Approved | BRIAN KELLY |
| Special/Order Compliance | 3/12/2026 | Partial Inspection | SEAN GRIFFITH |
| T-Bar Ceiling | 3/12/2026 | Approved | BRIAN KELLY |
| Final | 6/8/2026 | Partial Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/8/2026 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 6/8/2026 | Approved | BRIAN KELLY |
| Wood Frame | 6/8/2026 | Approved | BRIAN KELLY |
| Final | 6/12/2026 | OK to Issue CofO | BRIAN KELLY |