23533-23535 W STYLES ST 91367

Certificate Information: 23533-23535 W STYLES ST 91367

Application / Permit
24016-20000-09122
Plan Check / Job No.
B24VN03592
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert existing attached garage to new A.D.U. per GCS 65852.2(e)(1)(A). Design per WFPP.
Permit Issued
Issued on 4/9/2024
Issuing Office
Current Status
CofO Issued on 8/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2024 APPLICANT
Assigned to Plan Check Engineer 3/22/2024 CAROLEAN BASMA
Corrections Issued 3/22/2024 CAROLEAN BASMA
Plan Check Approved 4/8/2024 CAROLEAN BASMA
Issued 4/9/2024 APPLICANT
CofO in Progress 8/14/2024 GEVORK IPCHYAN
Permit Finaled 8/19/2024 JOHN JANSON
CofO Issued 8/19/2024 JOHN JANSON
Permit Finaled 8/19/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/2/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/2/2024 BRYAN GODINEZ
Sewer availability Cleared 4/2/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/23/2024 Corrections Issued GEVORK IPCHYAN
Pre-Inspection 4/23/2024 Not Ready for Inspection GEVORK IPCHYAN
Sewer 4/23/2024 Approved GEVORK IPCHYAN
Footing/Foundation/Slab 4/25/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 5/13/2024 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 5/13/2024 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 5/13/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 5/13/2024 Not Ready for Inspection GEVORK IPCHYAN
Wood Frame 5/13/2024 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 5/17/2024 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 5/17/2024 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Partial Approval GEVORK IPCHYAN
HVAC-Rough 5/17/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 5/17/2024 Approved GEVORK IPCHYAN
Wood Frame 5/17/2024 Partial Approval GEVORK IPCHYAN
Insulation 5/29/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 5/29/2024 Approved GEVORK IPCHYAN
Shower Pan 5/29/2024 Approved GEVORK IPCHYAN
Drywall Nailing 6/4/2024 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/2/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Final 8/2/2024 Approved GEVORK IPCHYAN
Final 8/2/2024 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Final 8/2/2024 Approved GEVORK IPCHYAN
PLUMBING-Final 8/2/2024 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 8/2/2024 Approved GEVORK IPCHYAN
Final 8/13/2024 OK to Issue CofO GEVORK IPCHYAN