14478 W JUDD ST 91331
Certificate Information: 14478 W JUDD ST 91331
- Application / Permit
- 24016-20000-08998
- Plan Check / Job No.
- B24VN03542
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED 18'X20' GARAGE INTO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER WFPP. THIS PERMIT TO INCLUDE REROOFING W/ CLASS'A' COOL ROOF COMPLIANT ASPHALT SHINGLES.
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 3/27/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 3/28/2024 | APPLICANT |
| Plan Check Approved | 4/5/2024 | GIOVANNY CHAVEZ |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 9/9/2024 | JENNIFER RABUCHIN |
| CofO Issued | 9/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 4/2/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/18/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/21/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/21/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/12/2024 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/12/2024 | Approved | MICHEL ABAJAN |
| Gas Test | 7/12/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/12/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 7/12/2024 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 7/12/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/12/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/18/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 7/18/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/18/2024 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 7/23/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| Final | 8/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 8/23/2024 | Approved | JENNIFER RABUCHIN |
| Final | 8/27/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 8/27/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/10/2024 | Approved | JENNIFER RABUCHIN |
| Final | 9/10/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 9/10/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/10/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/10/2024 | Approved | JENNIFER RABUCHIN |