13298 W REMINGTON ST 91331

Certificate Information: 13298 W REMINGTON ST 91331

Application / Permit
24016-20000-08869
Plan Check / Job No.
B24VN03476
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/29/2024
Issuing Office
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2024 APPLICANT
Assigned to Plan Check Engineer 3/20/2024 JESSE ARELLANO
Corrections Issued 3/21/2024 JESSE ARELLANO
Building Plans Picked Up 3/22/2024 APPLICANT
Issued 3/29/2024 APPLICANT
CofO in Progress 12/20/2024 MICHEL ABAJAN
No Progress 12/26/2024 ROBERT GOLD
CofO in Progress 12/26/2024 ROBERT GOLD
CofO in Progress 12/26/2024 ROBERT GOLD
Permit Finaled 1/2/2025 RUBEN SALAS
CofO Issued 1/2/2025 RUBEN SALAS
Permit Finaled 1/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/26/2024 CARLOS RAMIREZ
Sewer availability Cleared 3/26/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/28/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 5/28/2024 Approved JOHN COLEMAN
Sewer 5/28/2024 Approved JOHN COLEMAN
Underground Mechanical 5/28/2024 Approved JOHN COLEMAN
Footing/Foundation/Slab 6/6/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Approved WILLIAM WREN
PLUMBING-Rough 6/17/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/1/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/1/2024 Approved MICHEL ABAJAN
HVAC-Rough 7/1/2024 Approved MICHEL ABAJAN
METHANE-Rough 7/1/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 7/1/2024 Approved MICHEL ABAJAN
Insulation 7/8/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/8/2024 Approved MICHEL ABAJAN
Drywall Nailing 7/10/2024 Approved MICHEL ABAJAN
Shower Pan 7/10/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/23/2024 Approved MICHEL ABAJAN
Underground Mechanical 9/11/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 11/15/2024 Approved MICHEL ABAJAN
Final 11/15/2024 Corrections Issued MICHEL ABAJAN
HVAC-Final 11/15/2024 Approved MICHEL ABAJAN
PLUMBING-Final 11/15/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 11/15/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 11/15/2024 Approved MICHEL ABAJAN
Final 12/19/2024 OK to Issue CofO MICHEL ABAJAN