13298 W REMINGTON ST 91331
Certificate Information: 13298 W REMINGTON ST 91331
- Application / Permit
- 24016-20000-08869
- Plan Check / Job No.
- B24VN03476
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/29/2024
- Issuing Office
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2024 | JESSE ARELLANO |
| Corrections Issued | 3/21/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 3/22/2024 | APPLICANT |
| Issued | 3/29/2024 | APPLICANT |
| CofO in Progress | 12/20/2024 | MICHEL ABAJAN |
| No Progress | 12/26/2024 | ROBERT GOLD |
| CofO in Progress | 12/26/2024 | ROBERT GOLD |
| CofO in Progress | 12/26/2024 | ROBERT GOLD |
| Permit Finaled | 1/2/2025 | RUBEN SALAS |
| CofO Issued | 1/2/2025 | RUBEN SALAS |
| Permit Finaled | 1/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 3/26/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 5/28/2024 | Approved | JOHN COLEMAN |
| Sewer | 5/28/2024 | Approved | JOHN COLEMAN |
| Underground Mechanical | 5/28/2024 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 6/6/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 6/17/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/1/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/1/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/1/2024 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 7/1/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/1/2024 | Approved | MICHEL ABAJAN |
| Insulation | 7/8/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/8/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/10/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/10/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/23/2024 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 9/11/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 11/15/2024 | Approved | MICHEL ABAJAN |
| Final | 11/15/2024 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 11/15/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/15/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 11/15/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 11/15/2024 | Approved | MICHEL ABAJAN |
| Final | 12/19/2024 | OK to Issue CofO | MICHEL ABAJAN |