7544 N GLORIA AVE 91406

Certificate Information: 7544 N GLORIA AVE 91406

Application / Permit
24016-20000-08817
Plan Check / Job No.
B24VN03176
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 4/4/2024
Issuing Office
Current Status
Issued on 4/4/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/8/2024 APPLICANT
Assigned to Plan Check Engineer 3/14/2024 ISIS ARGUETA
Corrections Issued 3/14/2024 ISIS ARGUETA
Building Plans Picked Up 3/15/2024 APPLICANT
Applicant returned to address corrections 4/2/2024 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 4/3/2024 GIOVANNY CHAVEZ
Plan Check Approved 4/4/2024 ROSENDO MEDINA
Issued 4/4/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/20/2024 JOHN LIN
Sewer availability Cleared 3/20/2024 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 4/1/2024 LEE GUILBEAUX

Contact Information

Architect Flannery,, Charles Thomas; Lic. No.: C12638 22710 AVNEUE SAN LUIS      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/3/2024 Approved RAUL OLAGI
Underground Mechanical 5/13/2024 Partial Approval SALVADOR MARTINEZ
Insulation 6/27/2024 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 6/27/2024 Partial Approval SALVADOR MARTINEZ
Reinforced Concrete Frame 6/27/2024 Corrections Issued SALVADOR MARTINEZ
Wood Frame 6/27/2024 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 7/8/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/19/2024 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Approved SALVADOR MARTINEZ
Green Building Rough 8/19/2024 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 8/19/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 8/19/2024 Not Ready for Inspection SALVADOR MARTINEZ
Wood Frame 8/19/2024 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 9/10/2024 Approved SALVADOR MARTINEZ
HVAC-Rough 9/10/2024 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 9/10/2024 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 9/10/2024 Corrections Issued SALVADOR MARTINEZ
Rough-Elec/Plmb/HVAC 9/13/2024 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 9/26/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 9/26/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 10/1/2024 Approved SALVADOR MARTINEZ
Green Building Rough 10/1/2024 Approved SALVADOR MARTINEZ
HVAC-Rough 10/1/2024 Approved SALVADOR MARTINEZ
Insulation 10/7/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 10/16/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/12/2024 Approved SALVADOR MARTINEZ
Shower Pan 12/12/2024 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved CHRISTOPHER ROJAS
Final 7/21/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 7/21/2025 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 7/21/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 9/22/2025 Approved GAREN HAYRAPETYAN