CONVERT (E) REC ROOM TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) PER WFPP DESIGN. EXISTING GARAGE ATTACHED TO REMAIN.
Permit Issued
Issued on 8/22/2024
Issuing Office
Current Status
CofO Issued on 9/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2024 APPLICANT
Assigned to Plan Check Engineer 4/5/2024 ISIS ARGUETA
Corrections Issued 4/8/2024 ISIS ARGUETA
Applicant returned to address corrections 6/18/2024 MADISON ODELL
Plan Check Approved 8/20/2024 MADISON O'DELL
Issued 8/22/2024 APPLICANT
CofO in Progress 9/22/2025 JENNIFER RABUCHIN
Permit Finaled 9/24/2025 RUBEN SALAS
CofO Issued 9/24/2025 RUBEN SALAS
Permit Finaled 9/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/13/2024 CARLOS AGUILERA
Sewer availability Cleared 4/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/17/2024 CARLOS AGUILERA
Construction near power lines Cleared 8/14/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/27/2025 Not Ready for Inspection JENNIFER RABUCHIN
Final 1/27/2025 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Final 1/27/2025 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 1/27/2025 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 1/27/2025 Approved JENNIFER RABUCHIN
Smoke Detectors 1/27/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/23/2025 Approved JENNIFER RABUCHIN
Gas Test 5/23/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/23/2025 Approved JENNIFER RABUCHIN
Service/Power Release 5/23/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/7/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 7/7/2025 Approved JENNIFER RABUCHIN
Insulation 7/7/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/7/2025 Approved JENNIFER RABUCHIN
MERV13>=Rough 7/7/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/14/2025 Approved JENNIFER RABUCHIN
Shower Pan 7/14/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/16/2025 Corrections Issued JENNIFER RABUCHIN
Final 9/16/2025 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 9/16/2025 Approved JENNIFER RABUCHIN
HVAC-Final 9/16/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 9/16/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/19/2025 Approved JENNIFER RABUCHIN
Final 9/19/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 9/19/2025 Approved JENNIFER RABUCHIN
HVAC-Final 9/19/2025 Approved JENNIFER RABUCHIN
MERV13>=Final 9/19/2025 Approved JENNIFER RABUCHIN
Service/Power Release 9/19/2025 Approved JENNIFER RABUCHIN
Smoke Detectors 9/19/2025 Approved JENNIFER RABUCHIN