9943 N MARKLEIN AVE 91345
Certificate Information: 9943 N MARKLEIN AVE 91345
- Application / Permit
- 24016-20000-08689
- Plan Check / Job No.
- B24VN03388
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) REC ROOM TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) PER WFPP DESIGN. EXISTING GARAGE ATTACHED TO REMAIN.
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2024 | ISIS ARGUETA |
| Corrections Issued | 4/8/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 6/18/2024 | MADISON ODELL |
| Plan Check Approved | 8/20/2024 | MADISON O'DELL |
| Issued | 8/22/2024 | APPLICANT |
| CofO in Progress | 9/22/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
| CofO Issued | 9/24/2025 | RUBEN SALAS |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/13/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/14/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/27/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 1/27/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Final | 1/27/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 1/27/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 1/27/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/27/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/23/2025 | Approved | JENNIFER RABUCHIN |
| Gas Test | 5/23/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/23/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/23/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/14/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/14/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/16/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Gas Test | 9/16/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/16/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/19/2025 | Approved | JENNIFER RABUCHIN |
| Final | 9/19/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 9/19/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/19/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 9/19/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/19/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/19/2025 | Approved | JENNIFER RABUCHIN |