1051 E 41ST PL 90011

Certificate Information: 1051 E 41ST PL 90011

Application / Permit
24016-20000-08503
Plan Check / Job No.
B24VN03322
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Converting the existing Detached garage into an ADU per state law
Permit Issued
Issued on 6/24/2024
Issuing Office
Current Status
CofO Issued on 2/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2024 APPLICANT
Assigned to Plan Check Engineer 3/19/2024 RICARDO RAMIREZ
Corrections Issued 3/20/2024 RICARDO RAMIREZ
Plan Check Approved 6/10/2024 RICARDO RAMIREZ
Issued 6/24/2024 APPLICANT
CofO in Progress 2/10/2025 ALEJANDRO DE ARTOLA
Permit Finaled 2/13/2025 DEROLD HAUFF
CofO Issued 2/13/2025 DEROLD HAUFF
Permit Finaled 2/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/23/2024 TREVOR QUAN
Sewer availability Cleared 3/23/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/28/2024 TREVOR QUAN
"D" conditions Cleared 4/11/2024 YINGSHI HUANG
Historic Resource Verification Cleared 4/29/2024 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 5/14/2024 XIAOLIN LI
Redevelopment Project Area Cleared 6/3/2024 ELIZABETH GALLARDO

Contact Information

Contractor Bh Construction Co; Lic. No.: 553541-B       ,
Contractor Bhfc Inc; Lic. No.: 553541-B       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/19/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 7/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 7/22/2024 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 7/23/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/23/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/23/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/5/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/4/2024 Approved ALEJANDRO DE ARTOLA
Shower Pan 9/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 9/5/2024 Conditional Approval ALEX COLIN
BUILDING-Rough-Frame 9/19/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/19/2024 Approved ALEJANDRO DE ARTOLA
Shower Pan 9/19/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 9/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/23/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/27/2024 Not Ready for Inspection ANTHONY RAMOS
Drywall Nailing 9/27/2024 Not Ready for Inspection ANTHONY RAMOS
Insulation 9/27/2024 Not Ready for Inspection ANTHONY RAMOS
Interior/Exterior Lathing 9/27/2024 Not Ready for Inspection ANTHONY RAMOS
BUILDING-Rough-Frame 10/2/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/2/2024 Approved ALEJANDRO DE ARTOLA
Insulation 10/2/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/2/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/10/2024 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 12/10/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/21/2025 Approved MICHAEL LEWIS
Final 1/21/2025 Corrections Issued MICHAEL LEWIS
HVAC-Final 1/21/2025 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 1/21/2025 Approved MICHAEL LEWIS
Final 2/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 2/4/2025 Approved ALEJANDRO DE ARTOLA
Final 2/6/2025 OK to Issue CofO ALEJANDRO DE ARTOLA