1051 E 41ST PL 90011
Certificate Information: 1051 E 41ST PL 90011
- Application / Permit
- 24016-20000-08503
- Plan Check / Job No.
- B24VN03322
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Converting the existing Detached garage into an ADU per state law
- Permit Issued
- Issued on 6/24/2024
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2024 | RICARDO RAMIREZ |
| Corrections Issued | 3/20/2024 | RICARDO RAMIREZ |
| Plan Check Approved | 6/10/2024 | RICARDO RAMIREZ |
| Issued | 6/24/2024 | APPLICANT |
| CofO in Progress | 2/10/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
| CofO Issued | 2/13/2025 | DEROLD HAUFF |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 3/23/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2024 | TREVOR QUAN |
| "D" conditions | Cleared | 4/11/2024 | YINGSHI HUANG |
| Historic Resource Verification | Cleared | 4/29/2024 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 5/14/2024 | XIAOLIN LI |
| Redevelopment Project Area | Cleared | 6/3/2024 | ELIZABETH GALLARDO |
Contact Information
| Contractor | Bh Construction Co; Lic. No.: 553541-B | , |
| Contractor | Bhfc Inc; Lic. No.: 553541-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 7/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 9/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 9/5/2024 | Conditional Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 9/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 9/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 9/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/23/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/27/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Drywall Nailing | 9/27/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Insulation | 9/27/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/27/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/2/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 12/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/21/2025 | Approved | MICHAEL LEWIS |
| Final | 1/21/2025 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 1/21/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 1/21/2025 | Approved | MICHAEL LEWIS |
| Final | 2/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/6/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |