20252 W VANOWEN ST 91306
Certificate Information: 20252 W VANOWEN ST 91306
- Application / Permit
- 24016-20000-08371
- Plan Check / Job No.
- B24VN03265
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert portion of existing detached garage to A.D.U. per LAMC 12.22 A.33 (c) and (d). Design per WFPP.
- Permit Issued
- Issued on 11/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2024 | CAROLEAN BASMA |
| Corrections Issued | 3/16/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 8/30/2024 | CAROLEAN BASMA |
| Plan Check Approved | 9/13/2024 | CAROLEAN BASMA |
| Issued | 11/3/2024 | APPLICANT |
| CofO in Progress | 4/1/2025 | ALEXANDER HANDY |
| Permit Finaled | 5/27/2025 | JOHN JANSON |
| CofO Issued | 5/27/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/21/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/21/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2024 | CARLOS AGUILERA |
| ZI | Cleared | 9/9/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/26/2024 | Partial Inspection | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 12/27/2024 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/27/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 12/27/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/16/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 1/16/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 1/16/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/16/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 1/21/2025 | Corrections Issued | DAVID SCANTLIN |
| HVAC-Rough | 1/21/2025 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 1/21/2025 | Partial Inspection | JUAN ALVARADO |
| Insulation | 1/24/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 1/24/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 1/28/2025 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 3/7/2025 | Approved | ALEXANDER HANDY |
| Final | 3/7/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 3/7/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 3/7/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/7/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/7/2025 | Approved | ALEXANDER HANDY |
| Final | 3/13/2025 | Partial Approval | KRISTEN CAUSEY |
| ELECTRICAL-Final | 3/28/2025 | Approved | ALEXANDER HANDY |
| Final | 3/28/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 3/28/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/28/2025 | Approved | ALEXANDER HANDY |