9136-9138 N CEDROS AVE 91402

Certificate Information: 9136-9138 N CEDROS AVE 91402

Application / Permit
24016-20000-08368
Plan Check / Job No.
B24VN03263
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 5/6/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2024 APPLICANT
Assigned to Plan Check Engineer 3/15/2024 JEROME MAGAT PALMA
Corrections Issued 3/19/2024 JEROME MAGAT PALMA
Building Plans Picked Up 3/21/2024 APPLICANT
Plan Check Approved 5/2/2024 MADISON O'DELL
Issued 5/6/2024 APPLICANT
CofO in Progress 9/22/2025 JENNIFER RABUCHIN
Permit Finaled 10/14/2025 RUBEN SALAS
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/22/2024 CARLOS AGUILERA
Sewer availability Cleared 4/22/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/23/2024 CARLOS AGUILERA
"Q" conditions Cleared 4/30/2024 ALEX VELA
"T" removal Cleared 4/30/2024 ALEX VELA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/30/2024 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 11/21/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/10/2024 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 12/23/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/25/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 2/25/2025 Approved JENNIFER RABUCHIN
Green Building Rough 2/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 2/25/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/25/2025 Approved JENNIFER RABUCHIN
Insulation 3/4/2025 Approved LOUIS ESCOTO
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 4/2/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/2/2025 Approved JENNIFER RABUCHIN
Shower Pan 4/2/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/12/2025 Partial Inspection JENNIFER RABUCHIN
Final 9/12/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/12/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 9/12/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 9/12/2025 Approved JENNIFER RABUCHIN
Final 9/18/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved JOSE AVILA
BUILDING-Rough-Frame 9/23/2025 Approved JENNIFER RABUCHIN
Final 9/23/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 9/23/2025 Approved JENNIFER RABUCHIN