10149 N GAVIOTA AVE 91343

Certificate Information: 10149 N GAVIOTA AVE 91343

Application / Permit
24016-20000-08338
Plan Check / Job No.
B24VN03242
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Converting (E) 360SQFT Garage in to ADU PER STATE LAW ***FIRE SPRINKLER 13D REQUIRED****
Permit Issued
Issued on 4/17/2024
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2024 APPLICANT
Assigned to Plan Check Engineer 3/15/2024 KHUONG TRUONG
Corrections Issued 3/16/2024 KHUONG TRUONG
Plan Check Approved 4/8/2024 KHUONG TRUONG
Issued 4/17/2024 APPLICANT
CofO in Progress 11/5/2024 JAVIER RAMOS JR
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/28/2024 BIAINA HARITUNIAN
Sewer availability Cleared 3/28/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/29/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/14/2024 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 6/17/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 6/17/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 6/17/2024 Partial Approval JAVIER RAMOS JR
Sewer 6/17/2024 Approved JAVIER RAMOS JR
Special/Order Compliance 6/17/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 9/4/2024 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 9/10/2024 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/23/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 9/23/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 9/23/2024 Approved JAVIER RAMOS JR
Green Building Rough 9/23/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 9/23/2024 Approved JAVIER RAMOS JR
Wood Frame 9/23/2024 Corrections Issued JAVIER RAMOS JR
Insulation 9/30/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 9/30/2024 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 10/4/2024 Partial Approval LOUIS ESCOTO
ELECTRICAL-Final 10/15/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 10/30/2024 Approved JENNIFER RABUCHIN
Final 10/30/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/30/2024 Approved JENNIFER RABUCHIN
HVAC-Final 10/30/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 10/30/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/30/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/4/2024 Approved JAVIER RAMOS JR
Final 11/4/2024 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 11/4/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 11/4/2024 Approved JAVIER RAMOS JR
Service/Power Release 11/4/2024 Approved JAVIER RAMOS JR