10010-10012 N INDEPENDENCE AVE 91311

Certificate Information: 10010-10012 N INDEPENDENCE AVE 91311

Application / Permit
24016-20000-07873
Plan Check / Job No.
B24VN03025
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND CONVERT PORTION OF ATTACHED GARAGE AND SINGLE FAMILY DWELLING INTO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 AND THE REMAINING PORTION OF THE GARAGE INTO A STORAGE - PER ENGINEER
Permit Issued
Issued on 4/23/2024
Issuing Office
Current Status
CofO Issued on 4/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2024 APPLICANT
Assigned to Plan Check Engineer 3/8/2024 DANIEL ABRAMYAN
Corrections Issued 3/9/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 4/2/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 4/10/2024 GIOVANNY CHAVEZ
Plan Check Approved 4/22/2024 GIOVANNY CHAVEZ
Issued 4/23/2024 APPLICANT
CofO in Progress 3/28/2025 DAVID SCANTLIN
Permit Finaled 4/28/2025 JOHN JANSON
CofO Issued 4/28/2025 JOHN JANSON
Permit Finaled 4/28/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/12/2024 CARLOS AGUILERA
Sewer availability Cleared 3/12/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/13/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/25/2024 Approved DAVID SCANTLIN
Pre-Inspection 4/30/2024 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 5/29/2024 Approved DAVID SCANTLIN
Sewer 8/7/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 9/3/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 9/3/2024 Approved DAVID SCANTLIN
Green Building Rough 9/3/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 9/3/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 9/3/2024 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 9/3/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/11/2024 Corrections Issued DAVID SCANTLIN
BUILDING-Rough-Frame 9/17/2024 Approved DAVID SCANTLIN
Green Building Rough 9/17/2024 Approved DAVID SCANTLIN
Insulation 9/17/2024 Approved DAVID SCANTLIN
Drywall Nailing 9/25/2024 Approved SCOTT SOBEL
Shower Pan 10/29/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 11/6/2024 Approved SCOTT SOBEL
Deck 12/19/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/19/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Final 3/18/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 3/20/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 3/20/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 3/20/2025 Approved DAVID SCANTLIN
PLUMBING-Final 3/20/2025 Approved DAVID SCANTLIN
Smoke Detectors 3/20/2025 Approved DAVID SCANTLIN
Final 3/24/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 3/24/2025 Approved DAVID SCANTLIN
Final 3/28/2025 OK to Issue CofO DAVID SCANTLIN