7550 N GAVIOTA AVE 91406
Certificate Information: 7550 N GAVIOTA AVE 91406
- Application / Permit
- 24016-20000-07386
- Plan Check / Job No.
- B24VN02807
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 3/14/2024
- Issuing Office
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 3/9/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/11/2024 | APPLICANT |
| Plan Check Approved | 3/14/2024 | ALEC MOUSAKHANIAN |
| Issued | 3/14/2024 | APPLICANT |
| CofO in Progress | 8/8/2024 | SALVADOR MARTINEZ |
| Permit Finaled | 1/15/2025 | RUBEN SALAS |
| CofO Issued | 1/15/2025 | RUBEN SALAS |
| Permit Finaled | 1/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 3/12/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Atticare Construction; Lic. No.: 1051462-B | 4001 W. ALAMEDA AVE SUITE 106 BURBANK, CA 91505 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2024 | Corrections Issued | JOHN COLEMAN |
| Sewer | 4/1/2024 | Approved | JOHN COLEMAN |
| Underground Mechanical | 4/1/2024 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 4/3/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/15/2024 | Approved | SALVADOR MARTINEZ |
| Gas Test | 5/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 5/15/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 5/15/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/15/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/24/2024 | Partial Approval | SALVADOR MARTINEZ |
| Gas Test | 5/24/2024 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 5/24/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/30/2024 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 5/30/2024 | Approved | SALVADOR MARTINEZ |
| Insulation | 5/30/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/30/2024 | Partial Approval | SALVADOR MARTINEZ |
| Special/Order Compliance | 5/30/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Drywall Nailing | 6/6/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/6/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/25/2024 | Approved | SALVADOR MARTINEZ |
| Final | 7/25/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 7/25/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 7/25/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/25/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 7/25/2024 | Approved | SALVADOR MARTINEZ |
| Final | 7/30/2024 | OK to Issue CofO | SALVADOR MARTINEZ |
| HVAC-Final | 7/30/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/30/2024 | Approved | SALVADOR MARTINEZ |