15146 W MARTHA ST 91411
Certificate Information: 15146 W MARTHA ST 91411
- Application / Permit
- 24016-20000-06775
- Plan Check / Job No.
- B24VN02657
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2024 | JESSE ARELLANO |
| Corrections Issued | 3/7/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 3/13/2024 | APPLICANT |
| Plan Check Approved | 7/12/2024 | JESSE ARELLANO |
| Issued | 7/16/2024 | APPLICANT |
| CofO in Progress | 2/17/2026 | RYAN SALAZAR |
| Permit Finaled | 3/3/2026 | RUBEN SALAS |
| CofO Issued | 3/3/2026 | RUBEN SALAS |
| Permit Finaled | 3/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/15/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 7/11/2024 | EDGAR PASCUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mani,, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/31/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/1/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 8/12/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/13/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 8/26/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 9/19/2024 | Corrections Issued | VINCENT HANLEY |
| Insulation | 9/19/2024 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 9/27/2024 | Approved | RYAN SALAZAR |
| Insulation | 9/27/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/8/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/8/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 10/8/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/14/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 11/14/2024 | Approved | RYAN SALAZAR |
| Final | 11/14/2024 | Partial Approval | RYAN SALAZAR |
| Green Building Final | 11/14/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 11/14/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 11/14/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 11/14/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 11/14/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 11/14/2024 | Approved | RYAN SALAZAR |
| Final | 2/17/2026 | OK to Issue CofO | RYAN SALAZAR |