15146 W MARTHA ST 91411

Certificate Information: 15146 W MARTHA ST 91411

Application / Permit
24016-20000-06775
Plan Check / Job No.
B24VN02657
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 7/16/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2024 APPLICANT
Assigned to Plan Check Engineer 3/6/2024 JESSE ARELLANO
Corrections Issued 3/7/2024 JESSE ARELLANO
Building Plans Picked Up 3/13/2024 APPLICANT
Plan Check Approved 7/12/2024 JESSE ARELLANO
Issued 7/16/2024 APPLICANT
CofO in Progress 2/17/2026 RYAN SALAZAR
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/15/2024 BIAINA HARITUNIAN
Sewer availability Cleared 3/15/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/19/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 7/11/2024 EDGAR PASCUA

Contact Information

Contractor Owner-Builder       ,
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/31/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 8/1/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/1/2024 Approved VINCENT HANLEY
PLUMBING-Rough 8/12/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 8/13/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 8/26/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Partial Approval VINCENT HANLEY
HVAC-Rough 9/19/2024 Corrections Issued VINCENT HANLEY
Insulation 9/19/2024 Partial Approval VINCENT HANLEY
HVAC-Rough 9/27/2024 Approved RYAN SALAZAR
Insulation 9/27/2024 Approved RYAN SALAZAR
Drywall Nailing 10/8/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/8/2024 Approved RYAN SALAZAR
Shower Pan 10/8/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 11/14/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 11/14/2024 Approved RYAN SALAZAR
Final 11/14/2024 Partial Approval RYAN SALAZAR
Green Building Final 11/14/2024 Approved RYAN SALAZAR
Green Building Rough 11/14/2024 Approved RYAN SALAZAR
PLUMBING-Final 11/14/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 11/14/2024 Approved RYAN SALAZAR
Smoke Detectors 11/14/2024 Approved RYAN SALAZAR
Final 2/17/2026 OK to Issue CofO RYAN SALAZAR