5853 N RIVERTON AVE 91601

Certificate Information: 5853 N RIVERTON AVE 91601

Application / Permit
24016-20000-06521
Plan Check / Job No.
B24VN02558
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET GARAGE TO (N) 335 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 4/26/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2024 APPLICANT
Assigned to Plan Check Engineer 3/4/2024 JESSE ARELLANO
Corrections Issued 3/5/2024 JESSE ARELLANO
Building Plans Picked Up 3/11/2024 APPLICANT
Plan Check Approved 4/8/2024 LUISANGEL VALENZUELA
Issued 4/26/2024 APPLICANT
CofO in Progress 10/29/2024 JENNIFER RABUCHIN
CofO Issued 11/14/2024 DANIEL ORRANTE
Permit Finaled 11/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 3/26/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/27/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/8/2024 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 7/11/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 7/11/2024 Partial Approval JOSE AVILA
Footing/Foundation/Slab 7/17/2024 Approved JOSE AVILA
Sewer 7/22/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/29/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 8/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 9/6/2024 Partial Approval RYAN SALAZAR
Shower Pan 9/6/2024 Approved RYAN SALAZAR
Wood Frame 9/6/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 9/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 9/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 9/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 10/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 10/3/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 10/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/28/2024 Approved JENNIFER RABUCHIN
Final 10/28/2024 OK to Issue CofO JENNIFER RABUCHIN
Gas Test 10/28/2024 Approved JENNIFER RABUCHIN
HVAC-Final 10/28/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/28/2024 Approved JENNIFER RABUCHIN