5746 N IRVINE AVE 91601
Certificate Information: 5746 N IRVINE AVE 91601
- Application / Permit
- 24016-20000-06445
- Plan Check / Job No.
- B24VN02540
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing garage to ADU with addition per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/14/2024
- Issuing Office
- Current Status
- CofO Issued on 4/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 3/4/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 4/24/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/29/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 8/14/2024 | NEHEMIAS RAMOS |
| Issued | 8/14/2024 | APPLICANT |
| CofO in Progress | 3/17/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 4/16/2025 | RUBEN SALAS |
| CofO Issued | 4/16/2025 | RUBEN SALAS |
| Permit Finaled | 4/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/1/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/6/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 7/25/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: C38454 | 17337 VENTURA BLVD STE 310 ENCINO, CA 91316 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 12/13/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 12/16/2024 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 12/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 12/20/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 12/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 12/30/2024 | Approved | CHRISTOPHER ROJAS |
| Wood Frame | 1/9/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Partial Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/21/2025 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Rough | 1/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/31/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/31/2025 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 1/31/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 2/5/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/5/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 2/5/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 2/10/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 2/14/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/6/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 3/6/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 3/6/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 3/6/2025 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/6/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 3/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 3/13/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |