7320-7322 N OSO AVE 91306

Certificate Information: 7320-7322 N OSO AVE 91306

Application / Permit
24016-20000-06390
Plan Check / Job No.
B24VN02516
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED 2-CAR GARAGE INTO ACCESSORY DWELLING UNIT CA Govt. Code 65852.2(e)(1)(A). CONSTRUCTION DESIGN PER ENGINEER
Permit Issued
Issued on 3/29/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2024 APPLICANT
Assigned to Plan Check Engineer 3/1/2024 HAYATO TSUCHIYA
Corrections Issued 3/2/2024 HAYATO TSUCHIYA
Building Plans Picked Up 3/7/2024 APPLICANT
Applicant returned to address corrections 3/11/2024 ALFRED RAMIREZ
Issued 3/29/2024 APPLICANT
CofO in Progress 11/8/2024 ALEXANDER HANDY
Permit Finaled 1/3/2025 JOHN JANSON
CofO Issued 1/3/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/14/2024 CARLOS AGUILERA
Sewer availability Cleared 3/14/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/15/2024 CARLOS AGUILERA
Miscellaneous Cleared 3/21/2024 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2024 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 4/10/2024 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 4/12/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 4/12/2024 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 6/7/2024 Partial Approval ARUTYUN MADATYAN
Green Building Rough 6/7/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 6/7/2024 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 6/26/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 6/26/2024 Approved ARUTYUN MADATYAN
Green Building Rough 6/26/2024 Approved ARUTYUN MADATYAN
Wood Frame 6/26/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 7/2/2024 Approved ARUTYUN MADATYAN
Insulation 7/2/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 7/2/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 7/5/2024 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 7/25/2024 Approved ARUTYUN MADATYAN
Shower Pan 7/25/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 9/4/2024 Approved SCOTT SOBEL
ELECTRICAL-Final 11/4/2024 Not Ready for Inspection ALEXANDER HANDY
Final 11/4/2024 Corrections Issued ALEXANDER HANDY
Green Building Final 11/4/2024 Approved ALEXANDER HANDY
HVAC-Final 11/4/2024 Approved ALEXANDER HANDY
PLUMBING-Final 11/4/2024 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 11/4/2024 SGSOV No Gas ALEXANDER HANDY
Service/Power Release 11/4/2024 Not Required ALEXANDER HANDY
Smoke Detectors 11/4/2024 Approved ALEXANDER HANDY
ELECTRICAL-Final 11/7/2024 Approved ALEXANDER HANDY
Final 11/7/2024 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 11/7/2024 Approved ALEXANDER HANDY
PLUMBING-Final 11/7/2024 Approved ALEXANDER HANDY
Service/Power Release 11/7/2024 Approved ALEXANDER HANDY