7528 N RUFFNER AVE 91406
Certificate Information: 7528 N RUFFNER AVE 91406
- Application / Permit
- 24016-20000-06119
- Plan Check / Job No.
- B23VN18044
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** ePlan: Conversion and addition to existing detached garage to ADU per LAMC 12.22 A.33 (c) and (d).
- Permit Issued
- Issued on 11/14/2024
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2024 | EDWIN ESPIN |
| Corrections Issued | 3/4/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 8/7/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 11/6/2024 | AMY GUEVARRA |
| Plan Check Approved | 11/12/2024 | AMY GUEVARRA |
| Issued | 11/14/2024 | APPLICANT |
| CofO in Progress | 10/20/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
| CofO Issued | 11/4/2025 | RUBEN SALAS |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/26/2024 | RIDWAN HARDY |
| Address approval | Cleared | 10/25/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/25/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/25/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/25/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 1/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 1/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 1/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 2/6/2025 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 2/6/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/10/2025 | Partial Approval | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 2/21/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 2/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 3/4/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 3/5/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/7/2025 | Partial Approval | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 4/16/2025 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 5/14/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 5/21/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 6/4/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Rough | 6/4/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 6/17/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 6/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/24/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 6/24/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 6/24/2025 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/7/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 7/7/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/10/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 7/10/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/22/2025 | Partial Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 7/28/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/30/2025 | Partial Approval | SALVADOR MARTINEZ |
| Green Building Rough | 7/30/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 7/30/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/30/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 8/12/2025 | Conditional Approval | SALVADOR MARTINEZ |
| Drywall Nailing | 8/22/2025 | Approved | SALVADOR MARTINEZ |
| Special/Order Compliance | 8/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 9/8/2025 | Approved | WAYNE REGESTER |
| Shower Pan | 9/8/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 10/14/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 10/14/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/14/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/20/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Approved | GAREN HAYRAPETYAN |