10006 N WHEATLAND AVE 91040
Certificate Information: 10006 N WHEATLAND AVE 91040
- Application / Permit
- 24016-20000-05634
- Plan Check / Job No.
- B24VN02277
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ENCLOSE 196 SF IRREGULAR SHAPED PORTION OF (E) COVERED ROOF/BREEZEWAY AREA IN BETWEEN SINGLE FAMILY DWELLING AND ATTACHED GARAGE TO CREATE WALK IN CLOSET, LAUNDRY ROOM, AND EXPAND KITCHEN. ALL WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 10/23/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/2/2025
Permit Application Status History
| Submitted | 2/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2024 | OMAR GARNICA |
| Corrections Issued | 2/28/2024 | OMAR GARNICA |
| Plan Check Approved | 5/1/2024 | OMAR GARNICA |
| Issued | 10/23/2024 | APPLICANT |
| Permit Finaled | 5/1/2025 | DAVID ANDERSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/21/2024 | OMAR GARNICA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/7/2024 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 11/15/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 11/25/2024 | Partial Approval | DAVID ANDERSON |
| Insulation | 12/5/2024 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/10/2024 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Insulation | 12/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Corrections Issued | DAVID ANDERSON |
| Deputy Wood Construction | 2/4/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/18/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/26/2025 | Approved | DAVID ANDERSON |
| Insulation | 3/26/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 4/1/2025 | Approved | MATTHEW NELSON |
| Final | 5/1/2025 | Permit Finaled | DAVID ANDERSON |
| Green Building Final | 5/1/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 5/1/2025 | Approved | DAVID ANDERSON |