2651 S BARRY AVE 90064

Certificate Information: 2651 S BARRY AVE 90064

Application / Permit
24016-20000-05538
Plan Check / Job No.
B24VN02249
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). FIRE SPRINKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 4/17/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/23/2024 ARTIN ZARUKIAN
Corrections Issued 2/24/2024 ARTIN ZARUKIAN
Building Plans Picked Up 2/27/2024 APPLICANT
Plan Check Approved 4/17/2024 SERGIO MUNIZ
Issued 4/17/2024 APPLICANT
CofO in Progress 3/10/2026 ARAM AVEDISIAN
Permit Finaled 3/11/2026 RICHARD STEINBACH
CofO Issued 3/11/2026 RICHARD STEINBACH
Permit Finaled 3/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/4/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/4/2024 DARIN LAM
Roof/Waste drainage to street Cleared 3/4/2024 DARIN LAM
Sewer availability Cleared 3/4/2024 DARIN LAM
Specific Plan Cleared 4/9/2024 EDUARDO HERMOSO

Contact Information

Contractor A 1 Construction & Designs Inc; Lic. No.: 1002697-B 2817 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Telian,, Vartan; Lic. No.: C94330 11776 PIERCE ST      SYLMAR, CA 91342

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/25/2024 Not Ready for Inspection HERBERT GIRON
Sewer 7/25/2024 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 7/25/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 8/20/2024 Partial Approval JESUS PINEDA
Sewer 8/20/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 9/3/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Approved DANIEL VERA
HVAC-Rough 12/26/2024 Partial Approval SEAN HAUPT
PLUMBING-Rough 12/26/2024 Corrections Issued SEAN HAUPT
HVAC-Rough 1/8/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 1/8/2025 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 1/13/2025 Not Ready for Inspection DANIEL VERA
Excavation/Setback/Form/Re-Bar 1/14/2025 Approved DANIEL VERA
ELECTRICAL-Rough 1/23/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 1/23/2025 Approved ARAM AVEDISIAN
Deputy Steel/Welding 1/24/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 2/4/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 2/4/2025 Approved JESUS RODRIGUEZ
Green Building Rough 2/4/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/4/2025 Approved JESUS RODRIGUEZ
Special/Order Compliance 2/4/2025 Corrections Issued JESUS RODRIGUEZ
Verify Sprinkler Sign Off 2/4/2025 Approved JESUS RODRIGUEZ
Shower Pan 2/12/2025 Not Ready for Inspection DANIEL VERA
Drywall Nailing 2/21/2025 Partial Approval REGINA MENDEZ
Insulation 2/21/2025 Corrections Issued REGINA MENDEZ
Shower Pan 2/21/2025 Not Ready for Inspection REGINA MENDEZ
Drywall Nailing 2/27/2025 Approved EVAN COOPER
Insulation 2/27/2025 Approved EVAN COOPER
Shower Pan 4/8/2025 Approved WILBER ROSALES
ELECTRICAL-Final 2/17/2026 Corrections Issued ANTHONY EGSON
Final 2/17/2026 Corrections Issued ANTHONY EGSON
Gas Test 2/17/2026 Approved ANTHONY EGSON
Green Building Final 2/17/2026 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 2/17/2026 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 2/17/2026 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Approved ANTHONY EGSON
Service/Power Release 2/17/2026 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 2/17/2026 Not Ready for Inspection ANTHONY EGSON
Final 3/2/2026 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/2/2026 Not Ready for Inspection ARAM AVEDISIAN
Service/Power Release 3/2/2026 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 3/2/2026 Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/10/2026 Approved ARAM AVEDISIAN
Final 3/10/2026 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 3/10/2026 Approved ARAM AVEDISIAN
HVAC-Final 3/10/2026 Approved ARAM AVEDISIAN
PLUMBING-Final 3/10/2026 Approved ARAM AVEDISIAN
Service/Power Release 3/10/2026 Approved ARAM AVEDISIAN