22046 W MARTINEZ ST 91364
Certificate Information: 22046 W MARTINEZ ST 91364
- Application / Permit
- 24016-20000-05053
- Plan Check / Job No.
- B24VN02053
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: Remodel of existing 2-story single family dwelling with an attached garage. All work done per an engineered design.
- Permit Issued
- Issued on 6/14/2024
- Issuing Office
- Current Status
- Permit Finaled on 11/1/2024
Permit Application Status History
| Submitted | 2/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2024 | DANIEL SMILEY |
| Corrections Issued | 2/22/2024 | DANIEL SMILEY |
| Applicant returned to address corrections | 4/8/2024 | KELVIN CHUONG |
| Plan Check Approved | 4/12/2024 | LUKE GONZALES |
| Issued | 6/14/2024 | APPLICANT |
| Permit Finaled | 11/1/2024 | JOHN HAYES |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/12/2024 | DANIEL SMILEY |
Contact Information
| Contractor | Apadana Construction Group Inc; Lic. No.: 893662-B | , |
| Contractor | Eskandarian Rafee; Lic. No.: 893662-B | , |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/17/2024 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 6/24/2024 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 8/13/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Insulation | 8/13/2024 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 8/13/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 8/16/2024 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 8/16/2024 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 8/23/2024 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 8/23/2024 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 8/23/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/27/2024 | Corrections Issued | SCOTT SOBEL |
| BUILDING-Rough-Frame | 8/28/2024 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 8/28/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/29/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/29/2024 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 8/29/2024 | Approved | JOHN HAYES |
| Insulation | 8/30/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 9/3/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 9/19/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 10/21/2024 | Approved | JOHN HAYES |
| Final | 10/21/2024 | Corrections Issued | JOHN HAYES |
| PLUMBING-Final | 10/21/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 10/21/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 11/1/2024 | Approved | JOHN HAYES |
| Final | 11/1/2024 | Permit Finaled | JOHN HAYES |