13813 N GLADSTONE AVE 91342

Certificate Information: 13813 N GLADSTONE AVE 91342

Application / Permit
24016-20000-04730
Plan Check / Job No.
B24VN01882
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (E) detached garage to ADU per CA Govt. Code 65852.2(e)(1)(A), IB P/BC 2023-150 & WFPP in the front of the lot. COMPLY WITH DEPARTMENT ORDER effective date 03/18/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
Permit Issued
Issued on 3/22/2024
Issuing Office
Current Status
CofO Issued on 7/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/16/2024 JASON JANGADA
Corrections Issued 2/17/2024 JASON JANGADA
Applicant returned to address corrections 3/14/2024 JAHANSHAH POURHASSAN
Applicant returned to address corrections 3/20/2024 JASON JANGADA
Plan Check Approved 3/21/2024 JASON JANGADA
Issued 3/22/2024 APPLICANT
CofO in Progress 7/22/2025 KEVIN BERBERYAN
Permit Finaled 7/30/2025 RUBEN SALAS
CofO Issued 7/30/2025 RUBEN SALAS
Permit Finaled 7/30/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/13/2024 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 3/13/2024 GABRIELLA TORRES
Sewer availability Cleared 3/13/2024 GABRIELLA TORRES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/17/2024 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 5/17/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 6/13/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 6/17/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/17/2024 Partial Approval KEVIN BERBERYAN
ELECTRICAL-Rough 9/17/2024 Approved KEVIN BERBERYAN
Green Building Rough 9/17/2024 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Rough 9/17/2024 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 9/17/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/27/2024 Conditional Approval KEVIN BERBERYAN
Green Building Rough 9/27/2024 Approved KEVIN BERBERYAN
HVAC-Rough 9/27/2024 Corrections Issued KEVIN BERBERYAN
Insulation 9/27/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 9/27/2024 Approved KEVIN BERBERYAN
MERV13>=Rough 9/27/2024 Approved KEVIN BERBERYAN
HVAC-Rough 3/28/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 5/7/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 5/7/2025 Approved KEVIN BERBERYAN
Shower Pan 5/7/2025 Approved KEVIN BERBERYAN
Final 6/30/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 6/30/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
MERV13>=Final 6/30/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Smoke Detectors 6/30/2025 Approved NICHOLAS TROWBRIDGE
Final 7/16/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 7/16/2025 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Final 7/16/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Approved KEVIN BERBERYAN
Final 7/22/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 7/22/2025 Approved KEVIN BERBERYAN