6236 N BABCOCK AVE 91606

Certificate Information: 6236 N BABCOCK AVE 91606

Application / Permit
24016-20000-04722
Plan Check / Job No.
B24VN01880
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. EXISTING GARAGE TO BE CONVERTED TO ADU Per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/8/2024
Issuing Office
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/16/2024 NEHEMIAS RAMOS
Corrections Issued 2/17/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 7/2/2024 KELVIN CHUONG
Plan Check Approved 7/5/2024 NEHEMIAS RAMOS
Issued 7/8/2024 APPLICANT
CofO in Progress 5/21/2025 OGANES TARAKHCHYAN
Permit Finaled 6/5/2025 RUBEN SALAS
CofO Issued 6/5/2025 RUBEN SALAS
Permit Finaled 6/5/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/4/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 4/4/2024 CARLOS RAMIREZ
Sewer availability Cleared 4/4/2024 CARLOS RAMIREZ
Construction near power lines Cleared 6/25/2024 RIDWAN HARDY

Contact Information

Contractor Lush Remodeling & Development Inc; Lic. No.: 1005587-B       ,
Contractor Lush Remodeling Corporation; Lic. No.: 1005587-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/18/2024 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 7/23/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 7/30/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Sewer 7/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/2/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/15/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 10/15/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 10/15/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/18/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/18/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/21/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 10/21/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/22/2024 Corrections Issued GAREN HAYRAPETYAN
Shower Pan 10/23/2024 Approved GAREN HAYRAPETYAN
Insulation 10/24/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Insulation 10/28/2024 Corrections Issued GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/28/2024 Approved GAREN HAYRAPETYAN
Insulation 10/30/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 11/4/2024 Approved LOUIS ESCOTO
Final 3/13/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 3/13/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 3/13/2025 Approved GAREN HAYRAPETYAN
Final 4/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 5/6/2025 OK to Issue CofO OGANES TARAKHCHYAN
MERV13>=Final 5/6/2025 Approved OGANES TARAKHCHYAN