11369 N RESEDA BLVD 91326

Certificate Information: 11369 N RESEDA BLVD 91326

Application / Permit
24016-20000-04721
Plan Check / Job No.
B24VN01879
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E- Plan. CONVERT (E) 380 SQFT GARAGE TO ADU. Per CA Govt. Code 65852.2(e)(1)(A). Per Eng Calcs
Permit Issued
Issued on 4/9/2024
Issuing Office
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/16/2024 NEHEMIAS RAMOS
Corrections Issued 2/17/2024 NEHEMIAS RAMOS
Plan Check Approved 4/8/2024 NEHEMIAS RAMOS
Issued 4/9/2024 APPLICANT
CofO in Progress 10/1/2024 STEVEN BACK
Permit Finaled 10/3/2024 JOHN JANSON
CofO Issued 10/3/2024 JOHN JANSON
Permit Finaled 10/3/2024 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/23/2024 CHARLES POWELL
Address approval Cleared 3/9/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/9/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/9/2024 LEE GUILBEAUX
Sewer availability Cleared 3/9/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/9/2024 LEE GUILBEAUX
ZA Case Cleared 3/12/2024 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/23/2024 Partial Inspection STEVEN BACK
PLUMBING-Rough 4/29/2024 Partial Approval STEVEN BACK
Sewer 4/29/2024 Approved STEVEN BACK
ELECTRICAL-Rough 6/13/2024 Approved STEVEN BACK
PLUMBING-Rough 6/13/2024 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 6/28/2024 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval STEVEN BACK
Footing/Foundation/Slab 6/28/2024 Approved STEVEN BACK
PLUMBING-Rough 6/28/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 7/1/2024 Not Ready for Inspection STEVEN BACK
Green Building Rough 7/1/2024 Approved STEVEN BACK
MERV13>=Rough 7/1/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 7/5/2024 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Approved JEFFREY PARD
Insulation 7/5/2024 Approved JEFFREY PARD
Drywall Nailing 7/8/2024 Approved HENRY KIM
Interior/Exterior Lathing 7/16/2024 Approved STEVEN BACK
Final 8/16/2024 Corrections Issued STEVEN BACK
Green Building Final 8/16/2024 Not Ready for Inspection STEVEN BACK
MERV13>=Final 8/16/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Not Required STEVEN BACK
Smoke Detectors 8/16/2024 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 9/24/2024 No Access for Inspection TROY SANDERS
Final 9/24/2024 No Access for Inspection TROY SANDERS
Green Building Final 9/24/2024 No Access for Inspection TROY SANDERS
HVAC-Final 9/24/2024 No Access for Inspection TROY SANDERS
PLUMBING-Final 9/24/2024 No Access for Inspection TROY SANDERS
Smoke Detectors 9/24/2024 No Access for Inspection TROY SANDERS
Final 10/1/2024 OK to Issue CofO STEVEN BACK
Green Building Final 10/1/2024 Approved STEVEN BACK
Service/Power Release 10/1/2024 Approved STEVEN BACK
Smoke Detectors 10/1/2024 Approved STEVEN BACK