9713-9715 N AMBOY AVE 91331

Certificate Information: 9713-9715 N AMBOY AVE 91331

Application / Permit
24016-20000-04672
Plan Check / Job No.
B24VN01864
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22.
Permit Issued
Issued on 3/15/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 JEROME MAGAT PALMA
Corrections Issued 2/15/2024 JEROME MAGAT PALMA
Building Plans Picked Up 2/26/2024 APPLICANT
Plan Check Approved 3/15/2024 ROSENDO MEDINA
Issued 3/15/2024 APPLICANT
CofO in Progress 8/15/2025 KEVIN BERBERYAN
CofO Issued 8/20/2025 RUBEN SALAS
Permit Finaled 8/20/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/26/2024 BRYAN GODINEZ
Sewer availability Cleared 2/26/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/12/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/3/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/27/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 9/27/2024 Not Ready for Inspection MICHEL ABAJAN
Gas Test 9/27/2024 Approved MICHEL ABAJAN
Green Building Rough 9/27/2024 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 9/27/2024 Partial Approval MICHEL ABAJAN
Sewer 9/27/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/31/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/31/2024 Approved MICHEL ABAJAN
Green Building Rough 12/31/2024 Approved MICHEL ABAJAN
HVAC-Rough 12/31/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 12/31/2024 Approved MICHEL ABAJAN
Insulation 2/28/2025 Approved MICHEL ABAJAN
Drywall Nailing 3/28/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/7/2025 Approved MICHEL ABAJAN
Final 8/7/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 8/7/2025 Approved MICHEL ABAJAN
HVAC-Final 8/7/2025 Approved MICHEL ABAJAN
PLUMBING-Final 8/7/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 8/7/2025 Approved MICHEL ABAJAN
Final 8/14/2025 OK to Issue CofO KEVIN BERBERYAN