13010 W BURTON ST 91605

Certificate Information: 13010 W BURTON ST 91605

Application / Permit
24016-20000-04627
Plan Check / Job No.
B24VN01845
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Conversion of existing detached garage and storage to A.D.U. per CA Govt. code 65852.2 (e)(1)(A). Design per licensed engineer.
Permit Issued
Issued on 6/27/2024
Issuing Office
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 CAROLEAN BASMA
Corrections Issued 2/16/2024 CAROLEAN BASMA
Plan Check Approved 6/20/2024 CAROLEAN BASMA
Issued 6/27/2024 APPLICANT
CofO in Progress 8/15/2025 VINCENT HANLEY
Permit Finaled 8/29/2025 RUBEN SALAS
CofO Issued 8/29/2025 RUBEN SALAS
Permit Finaled 8/29/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/2/2024 CARLOS AGUILERA
Sewer availability Cleared 3/2/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/4/2024 CARLOS AGUILERA
Construction near power lines Cleared 6/13/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2025 No Access for Inspection VINCENT HANLEY
PLUMBING-Rough 2/14/2025 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 2/18/2025 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/20/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/20/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/24/2025 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 3/24/2025 Corrections Issued VINCENT HANLEY
Green Building Rough 3/24/2025 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 3/24/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 3/24/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 4/14/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 4/14/2025 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/21/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/21/2025 Approved VINCENT HANLEY
Green Building Rough 4/21/2025 Approved VINCENT HANLEY
HVAC-Rough 4/21/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/21/2025 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 4/21/2025 Approved VINCENT HANLEY
Insulation 4/29/2025 Approved MICHAEL CORTEZ
Drywall Nailing 5/8/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 5/13/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 7/11/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 7/11/2025 Approved VINCENT HANLEY
Final 7/11/2025 Corrections Issued VINCENT HANLEY
Green Building Final 7/11/2025 Approved VINCENT HANLEY
HVAC-Final 7/11/2025 Approved VINCENT HANLEY
PLUMBING-Final 7/11/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 7/11/2025 Approved VINCENT HANLEY
Final 8/14/2025 OK to Issue CofO VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV Not Required VINCENT HANLEY