114 3/4 E SYCAMORE PARK DR 90031

Certificate Information: 114 3/4 E SYCAMORE PARK DR 90031

Application / Permit
24016-20000-04593
Plan Check / Job No.
B24LA01285
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(2) Duplex
Work Description
CONVERT EXISTING STORAGE TO ACCESSORY DWELLING UNIT (443 SQFT) PER CA Govt. Code 65852.2(e)(1)(C)
Permit Issued
Issued on 1/7/2025
Issuing Office
Current Status
Issued on 1/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/24/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 PETER MOSESIAN
Corrections Issued 2/11/2024 PETER MOSESIAN
Quality Review Completed 2/14/2024 OMID HEDAYAT
Applicant returned to address corrections 11/26/2024 PETER MOSESIAN
Plan Check Approved 12/31/2024 PETER MOSESIAN
Issued 1/7/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/29/2024 JUSTIN BICOL
Sewer availability Cleared 4/29/2024 JUSTIN BICOL
Grading Pre-Inspection Cleared 4/30/2024 JONATHAN HOM
"Q" conditions Cleared 5/1/2024 RUBEN VASQUEZ
Address approval Cleared 5/16/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 5/25/2024 KURT CORRAL
HPOZ Cleared 6/4/2024 NATHALY DE LA PAZ
ZI Cleared 6/4/2024 NATHALY DE LA PAZ
Construction near power lines Cleared 8/21/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 9/5/2024 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/18/2024 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2025 Corrections Issued ALIZAH MAYAGOITIA
Sewer 5/20/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 5/20/2025 Partial Inspection OSVALDO PARAMO
PLUMBING-Rough 10/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Pre-Inspection 10/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Sewer 10/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Pre-Inspection 2/9/2026 Partial Approval PAUL BAZERKANIAN
Footing/Foundation/Slab 2/24/2026 Partial Approval SEAN POMISH
Masonry Wall/Backfill 2/27/2026 Partial Approval SEAN POMISH
Masonry Wall/Backfill 3/3/2026 Partial Approval SEAN POMISH
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval RAFAEL CORTES
Wood Frame 4/29/2026 Corrections Issued SEAN POMISH
Interior/Exterior Lathing 5/12/2026 Partial Approval SEAN POMISH