7425 N QUIMBY AVE 91307
Certificate Information: 7425 N QUIMBY AVE 91307
- Application / Permit
- 24016-20000-04516
- Plan Check / Job No.
- B24VN00976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ****ePlan**** Convert (e) detached 2-car garage to an ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/25/2024
- Issuing Office
- Current Status
- CofO Issued on 7/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | REZA HAGHIGHAT |
| Corrections Issued | 2/11/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 2/13/2024 | KAVIAN REFAHI |
| Plan Check Approved | 8/25/2024 | REZA HAGHIGHAT |
| Issued | 8/25/2024 | APPLICANT |
| CofO in Progress | 7/14/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/27/2025 | RUBEN SALAS |
| CofO Issued | 7/27/2025 | RUBEN SALAS |
| Permit Finaled | 7/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/2/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/5/2024 | GILBERT URREA |
| Construction near power lines | Cleared | 7/7/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chang,, Yeh; Lic. No.: S6868 | 168 S SIERRA MADRE BLVD 109 PASADENA, CA 91107 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/16/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/16/2024 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/20/2024 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 11/20/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/6/2024 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/6/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/6/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/9/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 12/9/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 12/9/2024 | Partial Approval | JEFFREY HARTLINE |
| Deputy Wood Construction | 12/12/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Sewer | 1/10/2025 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 1/10/2025 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/29/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/29/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 1/29/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 1/29/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 1/29/2025 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 1/29/2025 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 1/29/2025 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/29/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 7/11/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 7/11/2025 | Approved | CHRIS CHRISTENSEN |