3178 S STONER AVE 90066

Certificate Information: 3178 S STONER AVE 90066

Application / Permit
24016-20000-04003
Plan Check / Job No.
B24VN01651
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 2/28/2024
Issuing Office
Current Status
CofO Issued on 9/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2024 APPLICANT
Assigned to Plan Check Engineer 2/12/2024 ARTIN ZARUKIAN
Corrections Issued 2/13/2024 ARTIN ZARUKIAN
Building Plans Picked Up 2/14/2024 APPLICANT
Plan Check Approved 2/28/2024 ALEC MOUSAKHANIAN
Issued 2/28/2024 APPLICANT
CofO in Progress 9/3/2024 DANIEL VERA
Permit Finaled 9/7/2024 RICHARD STEINBACH
CofO Issued 9/7/2024 RICHARD STEINBACH
Permit Finaled 9/7/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/16/2024 DINAH GARIN
Sewer availability Cleared 2/16/2024 DINAH GARIN
Construction near power lines Cleared 2/21/2024 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/21/2024 DINAH GARIN
Grading Pre-Inspection Cleared 2/23/2024 CHARLES POWELL
Specific Plan Cleared 2/26/2024 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/3/2024 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 4/8/2024 Approved JESUS PINEDA
Deputy Drilled-In Anchors 4/9/2024 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 4/29/2024 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 4/29/2024 Approved JESUS PINEDA
Green Building Rough 4/29/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 4/29/2024 Approved JESUS PINEDA
PLUMBING-Rough 4/29/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/14/2024 Approved JESUS PINEDA
Green Building Rough 5/14/2024 Approved JESUS PINEDA
Insulation 5/14/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 5/14/2024 Partial Approval JESUS PINEDA
Drywall Nailing 5/20/2024 Approved JESUS PINEDA
Shower Pan 5/20/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 5/28/2024 Approved JESUS PINEDA
Sewer 6/5/2024 Approved JESUS PINEDA
Underground Mechanical 6/5/2024 Corrections Issued JESUS PINEDA
Underground Mechanical 6/10/2024 Approved JESUS PINEDA
ELECTRICAL-Final 8/2/2024 Corrections Issued JESUS PINEDA
Final 8/2/2024 Corrections Issued JESUS PINEDA
Green Building Final 8/2/2024 Corrections Issued JESUS PINEDA
HVAC-Final 8/2/2024 Approved JESUS PINEDA
PLUMBING-Final 8/2/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 8/2/2024 Approved JESUS PINEDA
Final 8/30/2024 OK to Issue CofO DANIEL VERA
Green Building Final 8/30/2024 Approved DANIEL VERA