6430-6432 N FARRALONE AVE 91303
Certificate Information: 6430-6432 N FARRALONE AVE 91303
- Application / Permit
- 24016-20000-03515
- Plan Check / Job No.
- B24VN01462
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/27/2024
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 2/9/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 2/10/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 2/17/2024 | ALEC MOUSAKHANIAN |
| Issued | 2/27/2024 | APPLICANT |
| CofO in Progress | 7/26/2024 | GEVORK IPCHYAN |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
| CofO Issued | 8/7/2024 | JOHN JANSON |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/12/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2024 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 2/12/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 2/12/2024 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/11/2024 | Conditional Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 3/12/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 3/26/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/1/2024 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 4/2/2024 | Approved | TROY SANDERS |
| Sewer | 4/2/2024 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 4/4/2024 | Conditional Approval | TROY SANDERS |
| Interior/Exterior Lathing | 4/5/2024 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | TROY SANDERS |
| Green Building Rough | 4/11/2024 | Approved | TROY SANDERS |
| Insulation | 4/15/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 4/19/2024 | Approved | TROY SANDERS |
| Final | 6/24/2024 | Order to Comply Issued | GEVORK IPCHYAN |
| Green Building Final | 6/24/2024 | Partial Approval | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 6/24/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 7/12/2024 | Approved | GEVORK IPCHYAN |
| Final | 7/12/2024 | Partial Approval | GEVORK IPCHYAN |
| Green Building Final | 7/12/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 7/12/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 7/12/2024 | Approved | GEVORK IPCHYAN |
| Final | 7/24/2024 | OK to Issue CofO | GEVORK IPCHYAN |