6337 N LONGRIDGE AVE 91401
Certificate Information: 6337 N LONGRIDGE AVE 91401
- Application / Permit
- 24016-20000-03500
- Plan Check / Job No.
- B24VN01451
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: 4'-11" X 17'-3" ADDITON TO SFD, 4-7"X 25'-1" ATTACHED TRELLIS PATIO COVER ADDITION, REMODEL 207 SF PORTION OF (E) ROOF TO RAISE CEILING HEIGHT TO 10', REMODEL TO (E) SFD INCLUDING INSTALLING (N) WINDOWS, DOORS, AND REVISING FLOOR PLAN LAYOUT - PER ENGINEER
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2024 | OMAR GARNICA |
| Corrections Issued | 2/8/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 3/15/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 3/23/2024 | PINANK PATEL |
| Issued | 3/26/2024 | APPLICANT |
| CofO in Progress | 3/17/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
| CofO Issued | 3/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2024 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 3/8/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 3/8/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2024 | Partial Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 4/3/2024 | Corrections Issued | JOSE AVILA |
| Deputy Drilled-In Anchors | 4/17/2024 | Conditional Approval | JOSE AVILA |
| Sewer | 4/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 4/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 5/2/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/3/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/3/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/3/2024 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/15/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 7/22/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/30/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/6/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 8/12/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 8/12/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/16/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/12/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 3/12/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/12/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 3/12/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 3/12/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/12/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 3/14/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |