5341 1/4 S 11TH AVE 90043
Certificate Information: 5341 1/4 S 11TH AVE 90043
- Application / Permit
- 24016-20000-03488
- Plan Check / Job No.
- B24VN01447
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PORTION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) AND STORAGE ROOM
- Permit Issued
- Issued on 6/27/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 2/10/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/13/2024 | APPLICANT |
| Plan Check Approved | 6/21/2024 | GURUNATH NESARAJAH |
| Issued | 6/27/2024 | APPLICANT |
| CofO in Progress | 5/1/2025 | LUIS CASTRO |
| No Progress | 5/3/2025 | DEROLD HAUFF |
| CofO in Progress | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 6/5/2025 | DEROLD HAUFF |
| CofO Issued | 6/5/2025 | DEROLD HAUFF |
| Permit Finaled | 6/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/15/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 2/15/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2024 | AMBER CAMPBELL |
| Redevelopment Project Area | Cleared | 3/14/2024 | ELIZABETH GALLARDO |
| Construction near power lines | Cleared | 6/5/2024 | RIDWAN HARDY |
| Historic Resource Verification | Cleared | 6/18/2024 | ELIZABETH GALLARDO |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD 230 TARZANA, CA 91356 |
| Engineer | Gosen,, James; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/14/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 8/26/2024 | Corrections Issued | ANTHONY EGSON |
| Sewer | 8/30/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 8/30/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 9/5/2024 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 9/6/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/6/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/11/2024 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 9/20/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/18/2024 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/1/2024 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 11/1/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 11/1/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 11/6/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 11/6/2024 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 11/15/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 11/15/2024 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 11/15/2024 | Approved | BARRY HACHE |
| Wood Frame | 11/15/2024 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | BARRY HACHE |
| Green Building Rough | 11/20/2024 | Not Ready for Inspection | BARRY HACHE |
| Wood Frame | 11/20/2024 | Not Ready for Inspection | BARRY HACHE |
| Insulation | 11/27/2024 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 11/27/2024 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 12/3/2024 | Partial Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2024 | Approved | LUIS CASTRO |
| Shower Pan | 12/19/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 1/2/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 1/29/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 3/28/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 3/28/2025 | Approved | LUIS CASTRO |
| Final | 3/28/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 3/28/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 3/28/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 3/28/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 3/28/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 3/28/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 3/28/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 4/2/2025 | Approved | LUIS CASTRO |
| Final | 4/2/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 4/2/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/2/2025 | Approved | LUIS CASTRO |
| Final | 5/1/2025 | OK to Issue CofO | LUIS CASTRO |