1903 S BURNSIDE AVE 90016

Certificate Information: 1903 S BURNSIDE AVE 90016

Application / Permit
24016-20000-03457
Plan Check / Job No.
B24VN01424
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/24/2024
Issuing Office
Current Status
CofO Issued on 4/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 JEROME MAGAT PALMA
Corrections Issued 2/9/2024 JEROME MAGAT PALMA
Building Plans Picked Up 2/14/2024 APPLICANT
Plan Check Approved 6/24/2024 ISIS ARGUETA
Issued 6/24/2024 APPLICANT
CofO in Progress 3/4/2025 ARTHUR NEGRETE
Permit Finaled 4/1/2025 DEROLD HAUFF
CofO Issued 4/1/2025 DEROLD HAUFF
Permit Finaled 4/1/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/27/2024 JUSTIN BICOL
Sewer availability Cleared 2/27/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 2/28/2024 JUSTIN BICOL
Construction near power lines Cleared 6/13/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/23/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 8/27/2024 Not Ready for Inspection LUIS CASTRO
Sewer 8/27/2024 Approved LUIS CASTRO
Footing/Foundation/Slab 8/30/2024 Partial Inspection ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 9/17/2024 Corrections Issued ARTHUR NEGRETE
Deputy Drilled-In Anchors 9/18/2024 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 9/19/2024 Approved ARTHUR NEGRETE
Wood Frame 9/30/2024 Partial Approval ARTHUR NEGRETE
ELECTRICAL-Rough 10/10/2024 Approved ARTHUR NEGRETE
Green Building Rough 10/10/2024 Approved ARTHUR NEGRETE
HVAC-Rough 10/10/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 10/10/2024 Approved ARTHUR NEGRETE
Underground Mechanical 10/10/2024 Approved ARTHUR NEGRETE
Insulation 10/15/2024 Conditional Approval JOSH MEISTER
BUILDING-Rough-Frame 10/31/2024 Approved ARTHUR NEGRETE
Drywall Nailing 10/31/2024 Approved ARTHUR NEGRETE
Green Building Final 10/31/2024 Approved ARTHUR NEGRETE
Insulation 10/31/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 11/7/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 12/23/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 12/23/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 12/24/2024 Approved ARTHUR NEGRETE
HVAC-Final 12/24/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 12/24/2024 Approved ARTHUR NEGRETE
Final 12/27/2024 Corrections Issued ARTHUR NEGRETE
Final 2/28/2025 OK to Issue CofO ARTHUR NEGRETE