8638-8640 N CASABA AVE 91306

Certificate Information: 8638-8640 N CASABA AVE 91306

Application / Permit
24016-20000-03045
Plan Check / Job No.
B24VN01227
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE AND BREEZEWAY TO ACCESSORY DWELLING UNIT (533 SQ FT) PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 3/28/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2024 APPLICANT
Assigned to Plan Check Engineer 2/2/2024 JEROME MAGAT PALMA
Corrections Issued 2/6/2024 JEROME MAGAT PALMA
Building Plans Picked Up 2/7/2024 APPLICANT
Plan Check Approved 3/28/2024 ALEC MOUSAKHANIAN
Issued 3/28/2024 APPLICANT
CofO in Progress 11/14/2025 CHRIS CHRISTENSEN
Permit Finaled 11/14/2025 JOHN JANSON
CofO Issued 11/14/2025 JOHN JANSON
Permit Finaled 11/14/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/28/2024 GABRIELLA TORRES
Sewer availability Cleared 2/28/2024 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 3/15/2024 JOHN LIN
Hold Cleared 3/25/2025 TERESA RIVAS

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/21/2025 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/21/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/21/2025 Approved CHRIS CHRISTENSEN
Sewer 4/21/2025 Approved CHRIS CHRISTENSEN
Underground Mechanical 4/21/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/24/2025 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/24/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 6/24/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/11/2025 Approved JEFFREY HARTLINE
Green Building Rough 7/11/2025 Approved JEFFREY HARTLINE
Insulation 7/11/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 7/11/2025 Partial Approval JEFFREY HARTLINE
Drywall Nailing 8/29/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/29/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/24/2025 Approved CHRIS CHRISTENSEN
Final 10/24/2025 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/24/2025 Approved CHRIS CHRISTENSEN
HVAC-Final 10/24/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/24/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 10/24/2025 Approved CHRIS CHRISTENSEN
Final 10/28/2025 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Approved CHRIS CHRISTENSEN