18214-18216 W RAYEN ST 91325

Certificate Information: 18214-18216 W RAYEN ST 91325

Application / Permit
24016-20000-02884
Plan Check / Job No.
B24VN01173
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO A (N) ACCCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/16/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2024 APPLICANT
Assigned to Plan Check Engineer 2/2/2024 JESSE ARELLANO
Corrections Issued 2/6/2024 JESSE ARELLANO
Building Plans Picked Up 2/13/2024 APPLICANT
Plan Check Approved 2/16/2024 GIOVANNY CHAVEZ
Issued 2/16/2024 APPLICANT
CofO in Progress 7/22/2024 DAVID SCANTLIN
Permit Finaled 8/1/2024 JOHN JANSON
CofO Issued 8/1/2024 JOHN JANSON
Permit Finaled 8/1/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/14/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 2/14/2024 BRYAN GODINEZ
Sewer availability Cleared 2/14/2024 BRYAN GODINEZ

Contact Information

Contractor Monette Daniel Construction; Lic. No.: 877752-B 16759 GRESHAM ST      NORTH HILLS, CA 91343

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2024 Approved DAVID SCANTLIN
Footing/Foundation/Slab 3/1/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/21/2024 Conditional Approval KRISTEN CAUSEY
Green Building Rough 3/21/2024 Partial Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 3/27/2024 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Rough 4/19/2024 Approved KRISTEN CAUSEY
HVAC-Rough 4/19/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 4/19/2024 Approved KRISTEN CAUSEY
Insulation 4/23/2024 No Access for Inspection KRISTEN CAUSEY
Drywall Nailing 4/26/2024 Approved KRISTEN CAUSEY
Insulation 4/26/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 6/28/2024 Approved DAVID SCANTLIN
Final 6/28/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 6/28/2024 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 6/28/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 6/28/2024 Approved DAVID SCANTLIN
Green Building Final 7/2/2024 Not Ready for Inspection KRISTEN CAUSEY
Final 7/22/2024 OK to Issue CofO DAVID SCANTLIN
Green Building Final 7/22/2024 Approved DAVID SCANTLIN