22438-22440 W CALIFA ST 91367

Certificate Information: 22438-22440 W CALIFA ST 91367

Application / Permit
24016-20000-02872
Plan Check / Job No.
B24VN01162
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Conversion of Attached Garage into ADU & Laundry Room per GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 3/2/2024
Issuing Office
Current Status
CofO in Progress on 7/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/31/2024 APPLICANT
Assigned to Plan Check Engineer 2/5/2024 ZAW HAN
Corrections Issued 2/5/2024 ZAW HAN
Plan Check Approved 2/19/2024 ZAW HAN
Issued 3/2/2024 APPLICANT
CofO in Progress 2/20/2025 TROY SANDERS
No Progress 7/7/2025 ROBERT GOLD
CofO in Progress 7/7/2025 ROBERT GOLD

Permit Application Clearance Information

Sewer availability Cleared 2/6/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/8/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/8/2024 CARLOS RAMIREZ
Address approval Cleared 2/12/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 2/19/2024 ZAW HAN
Hold Cleared 4/5/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/9/2024 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 5/24/2024 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 5/24/2024 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 5/24/2024 Corrections Issued GEVORK IPCHYAN
BUILDING-Rough-Frame 6/10/2024 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 6/10/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 6/10/2024 Partial Approval GEVORK IPCHYAN
Footing/Foundation/Slab 6/13/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 6/24/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 6/24/2024 Partial Approval GEVORK IPCHYAN
Insulation 7/11/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 7/11/2024 Partial Approval GEVORK IPCHYAN
Rough-Elec/Plmb/HVAC 7/11/2024 Approved GEVORK IPCHYAN
Shower Pan 7/11/2024 Approved GEVORK IPCHYAN
Deputy Wood Construction 7/17/2024 Conditional Approval TROY SANDERS
Drywall Nailing 7/25/2024 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval TROY SANDERS
Final 9/13/2024 Not Ready for Inspection TROY SANDERS
Green Building Final 9/13/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved TROY SANDERS
Smoke Detectors 9/13/2024 Approved TROY SANDERS
Final 2/19/2025 OK to Issue CofO TROY SANDERS
Special/Order Compliance 8/20/2025 Corrections Issued TROY SANDERS