13806 1/2 W LOUVRE ST 91331
Certificate Information: 13806 1/2 W LOUVRE ST 91331
- Application / Permit
- 24016-20000-02762
- Plan Check / Job No.
- B24VN01130
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING GARAGE TO NEW DWELLING UNIT PER SB9
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Current Status
- CofO Issued on 12/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | SELLA BENYAMIN |
| Corrections Issued | 2/6/2024 | SELLA BENYAMIN |
| Quality Review Completed | 2/7/2024 | STEVEN KIM |
| Plan Check Approved | 8/6/2024 | SELLA BENYAMIN |
| Issued | 8/6/2024 | APPLICANT |
| CofO in Progress | 10/22/2025 | RAUL OLAGI |
| No Progress | 10/22/2025 | RAUL OLAGI |
| CofO in Progress | 10/22/2025 | RAUL OLAGI |
| CofO Issued | 12/2/2025 | RUBEN SALAS |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/13/2024 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 5/14/2024 | DORIAN AGUILAR |
| Hydrant and Access approval | Cleared | 6/23/2024 | KURT CORRAL |
| Construction near power lines | Cleared | 7/2/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/4/2024 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/28/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 2/28/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 2/28/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Sewer | 2/28/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Underground Mechanical | 2/28/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Wood Frame | 2/28/2025 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/3/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/3/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/3/2025 | Approved | MICHEL ABAJAN |
| Sewer | 3/3/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/3/2025 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 3/3/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 4/2/2025 | Partial Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/2/2025 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 4/2/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/9/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/9/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/11/2025 | No Access for Inspection | MICHEL ABAJAN |
| Final | 8/11/2025 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 8/11/2025 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 8/11/2025 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 8/11/2025 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 8/11/2025 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/27/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 8/27/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 8/27/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 8/27/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 8/27/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/27/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 8/27/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/15/2025 | Approved | MICHEL ABAJAN |
| Final | 10/15/2025 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 10/15/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/15/2025 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/15/2025 | Approved | MICHEL ABAJAN |
| Final | 10/17/2025 | OK to Issue CofO | MICHEL ABAJAN |