1825 N AVENUE 46 90041
Certificate Information: 1825 N AVENUE 46 90041
- Application / Permit
- 24016-20000-02703
- Plan Check / Job No.
- B24VN01096
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH STORAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | JESSE ARELLANO |
| Corrections Issued | 2/3/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 2/7/2024 | APPLICANT |
| Applicant returned to address corrections | 6/18/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/27/2024 | MIROOSH KHACHATOORIAN |
| Issued | 7/9/2024 | APPLICANT |
| CofO in Progress | 9/26/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
| CofO Issued | 10/1/2024 | RUBEN SALAS |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 2/6/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 5/29/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2024 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/23/2024 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 7/23/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 7/23/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Underground Mechanical | 7/30/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/2/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 8/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/12/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/12/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/12/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/13/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/13/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 8/14/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/14/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/15/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/16/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 9/16/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/16/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 9/20/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 9/20/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/24/2024 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 9/24/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 9/24/2024 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 9/24/2024 | No Access for Inspection | ROY SPAULDING |
| Final | 9/25/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/25/2024 | Approved | ALIZAH MAYAGOITIA |