15404-15406 W LULL ST 91406
Certificate Information: 15404-15406 W LULL ST 91406
- Application / Permit
- 24016-20000-02425
- Plan Check / Job No.
- B24VN00958
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Convert attached garage into JADU PER STATE LAW
- Permit Issued
- Issued on 5/3/2024
- Issuing Office
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2024 | KHUONG TRUONG |
| Corrections Issued | 2/1/2024 | KHUONG TRUONG |
| Applicant returned to address corrections | 4/19/2024 | KHUONG TRUONG |
| Applicant returned to address corrections | 4/27/2024 | KHUONG TRUONG |
| Plan Check Approved | 5/2/2024 | KHUONG TRUONG |
| Issued | 5/3/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | VINCENT HANLEY |
| Permit Finaled | 3/11/2025 | RUBEN SALAS |
| Permit Finaled | 3/11/2025 | RUBEN SALAS |
| CofO Issued | 3/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 3/30/2024 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/5/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 6/7/2024 | Partial Approval | VINCENT HANLEY |
| Sewer | 6/7/2024 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Corrections Issued | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 6/13/2024 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/13/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/16/2024 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/16/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 8/16/2024 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/20/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 8/20/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/20/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 8/20/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 8/28/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/1/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/1/2024 | Partial Approval | VINCENT HANLEY |
| Insulation | 10/15/2024 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 11/7/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 11/7/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/14/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 2/20/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/20/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/20/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 2/20/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 2/26/2025 | Approved | VINCENT HANLEY |
| Final | 2/26/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 2/26/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/26/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/26/2025 | Approved | VINCENT HANLEY |