7019-7021 N GREEN VISTA CIR 91307

Certificate Information: 7019-7021 N GREEN VISTA CIR 91307

Application / Permit
24016-20000-02278
Plan Check / Job No.
B24VN00894
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert (E) attached garage and a portion of (E) SFD to ADU per LAMC 12.22 A.33(c) and (e).
Permit Issued
Issued on 3/7/2024
Issuing Office
Current Status
CofO Issued on 10/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2024 APPLICANT
Assigned to Plan Check Engineer 1/26/2024 CAROLEAN BASMA
Corrections Issued 1/27/2024 CAROLEAN BASMA
Plan Check Approved 2/25/2024 CAROLEAN BASMA
Issued 3/7/2024 APPLICANT
CofO in Progress 10/21/2025 CHRIS CHRISTENSEN
Permit Finaled 10/30/2025 MICHAEL PELHAM
CofO Issued 10/30/2025 MICHAEL PELHAM
Permit Finaled 10/30/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 1/30/2024 CARLOS RAMIREZ
Sewer availability Cleared 1/30/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/8/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 2/8/2024 CHARLES POWELL

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor 52 Star Construction Inc; Lic. No.: 1042404-B       ,
Contractor Ventura Stone Construction; Lic. No.: 1042404-B       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 2/20/2025 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/20/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 2/20/2025 Partial Approval CHRIS CHRISTENSEN
Sewer 2/20/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/20/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/20/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 3/20/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 3/20/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/2/2025 Partial Approval GEVORK IPCHYAN
Shower Pan 4/2/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 4/4/2025 Approved JEFFREY HARTLINE
Green Building Rough 4/4/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 4/4/2025 Partial Approval JEFFREY HARTLINE
Insulation 4/9/2025 Corrections Issued CHRIS CHRISTENSEN
Insulation 4/16/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 4/25/2025 Approved SCOTT SOBEL
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 10/1/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Final 10/20/2025 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/20/2025 Approved CHRIS CHRISTENSEN