17333 W COHASSET ST 91406

Certificate Information: 17333 W COHASSET ST 91406

Application / Permit
24016-20000-02171
Plan Check / Job No.
B24VN00840
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (E) Detached Garage to (N) ADU per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 8/29/2024
Issuing Office
Current Status
CofO Issued on 7/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2024 APPLICANT
Assigned to Plan Check Engineer 1/29/2024 AMY GUEVARRA
Corrections Issued 2/2/2024 AMY GUEVARRA
Applicant returned to address corrections 5/30/2024 MICHAEL LOPEZ
Applicant returned to address corrections 6/3/2024 AMY GUEVARRA
Plan Check Approved 6/6/2024 AMY GUEVARRA
Issued 8/29/2024 APPLICANT
CofO in Progress 7/10/2025 SALVADOR MARTINEZ
Permit Finaled 7/11/2025 RUBEN SALAS
CofO Issued 7/11/2025 RUBEN SALAS
Permit Finaled 7/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/23/2024 BIAINA HARITUNIAN
Construction within easement Cleared 5/23/2024 RIDWAN HARDY
Sewer availability Cleared 5/23/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/24/2024 BIAINA HARITUNIAN

Contact Information

Contractor Jc Builders & Renovation Inc; Lic. No.: 1091494-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/17/2024 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 10/18/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 10/18/2024 Partial Approval SALVADOR MARTINEZ
Sewer 10/18/2024 Approved SALVADOR MARTINEZ
Underground Mechanical 10/18/2024 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 10/29/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 11/26/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 11/26/2024 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 11/26/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 11/26/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 1/15/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 1/15/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 1/15/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 1/15/2025 Approved SALVADOR MARTINEZ
Insulation 1/24/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 1/24/2025 Corrections Issued SALVADOR MARTINEZ
Drywall Nailing 2/5/2025 Approved GAREN HAYRAPETYAN
Shower Pan 2/5/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 2/10/2025 Partial Approval SALVADOR MARTINEZ
ELECTRICAL-Final 6/18/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Final 6/18/2025 Approved SALVADOR MARTINEZ
PLUMBING-Final 6/18/2025 Corrections Issued SALVADOR MARTINEZ
Service/Power Release 6/18/2025 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/27/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 6/27/2025 Corrections Issued SALVADOR MARTINEZ
Final 6/27/2025 Corrections Issued SALVADOR MARTINEZ
Gas Test 6/27/2025 Approved SALVADOR MARTINEZ
Green Building Final 6/27/2025 Approved SALVADOR MARTINEZ
Green Building Rough 6/27/2025 Approved SALVADOR MARTINEZ
PLUMBING-Final 6/27/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 6/27/2025 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 6/27/2025 Approved SALVADOR MARTINEZ
Final 7/7/2025 OK to Issue CofO SALVADOR MARTINEZ
Service/Power Release 7/7/2025 Approved SALVADOR MARTINEZ