15944-15946 W LAHEY ST 91344

Certificate Information: 15944-15946 W LAHEY ST 91344

Application / Permit
24016-20000-01392
Plan Check / Job No.
B24VN00536
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: GARAGE CONVERSION TO ADU AND REFRAME NEW FLAT ROOF PER STATE LAW WORK DONE PER WFPP
Permit Issued
Issued on 2/28/2024
Issuing Office
Current Status
CofO Issued on 9/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2024 APPLICANT
Assigned to Plan Check Engineer 1/22/2024 KHUONG TRUONG
Corrections Issued 1/23/2024 KHUONG TRUONG
Applicant returned to address corrections 2/23/2024 KHUONG TRUONG
Plan Check Approved 2/27/2024 KHUONG TRUONG
Issued 2/28/2024 APPLICANT
CofO in Progress 8/22/2024 JENNIFER RABUCHIN
Permit Finaled 9/9/2024 DANIEL ORRANTE
CofO Issued 9/9/2024 DANIEL ORRANTE
Permit Finaled 9/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/7/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/7/2024 LEE GUILBEAUX
Sewer availability Cleared 2/7/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/8/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/8/2024 LEE GUILBEAUX
Grading Pre-Inspection Cleared 2/10/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/1/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 4/16/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/8/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/29/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/29/2024 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 5/29/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 6/10/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 6/10/2024 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 6/10/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 6/13/2024 Approved JENNIFER RABUCHIN
Wood Frame 6/13/2024 Approved JENNIFER RABUCHIN
Insulation 6/26/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/26/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 7/5/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/5/2024 Corrections Issued JENNIFER RABUCHIN
Shower Pan 7/5/2024 Approved JENNIFER RABUCHIN
Pre-Inspection 7/17/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/16/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 8/16/2024 Approved JENNIFER RABUCHIN
HVAC-Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 8/16/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/20/2024 Approved JENNIFER RABUCHIN
Final 8/20/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 8/20/2024 Approved JENNIFER RABUCHIN
HVAC-Final 8/20/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/20/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/20/2024 SGSOV Approved JENNIFER RABUCHIN