16310 W RAYMER ST 91406

Certificate Information: 16310 W RAYMER ST 91406

Application / Permit
24016-20000-00995
Plan Check / Job No.
B23VN17979
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
eplan. VAULT ADDITION, TENANT IMPROVEMENT AT EXISTING MANUFACTURING/OFFICE TO REMAIN. NEW MILLWORK, ROOF EQUIPMENT, NEW VAULT BELOW GRADE. COMBINE 2 TENANT SPACES INTO ONE AREA. (TI FOR A PORTION OF THE AREA UNDER SEPARATE PERMIT, PARKING RESTRIPING UNDER SEPARATE PERMIT)
Permit Issued
Issued on 1/15/2025
Issuing Office
Current Status
Issued on 1/15/2025

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 PRANITA SHAH
Assigned to Zoning Architect 2/15/2024 PRANITA SHAH
Corrections Issued 2/20/2024 PRANITA SHAH
Quality Review Completed 2/29/2024 GARO TELMI
Applicant returned to address corrections 8/1/2024 PRANITA SHAH
Applicant returned to address corrections 8/15/2024 PRANITA SHAH
Applicant returned to address corrections 12/12/2024 PRANITA SHAH
Plan Check Approved 12/19/2024 PRANITA SHAH
Issued 1/15/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/1/2024 BIAINA HARITUNIAN
Green Code Cleared 8/15/2024 MICHAEL AYERS
DAS Clearance Cleared 9/5/2024 Michael Perez
Sewer availability Cleared 11/4/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 11/22/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/22/2024 EDGAR ALCARAZ
Zoning Plan Check Cleared 12/19/2024 Michael Perez

Contact Information

Architect Bodien,, Mark John; Lic. No.: C31158 4128 FAIRFAX DRIVE      COLUMBUS, OH 432204525
Contractor Clune Construction Co. Lp; Lic. No.: 732107-B       ,
Contractor Clune Construction Company L P; Lic. No.: 732107-B       ,
Engineer Amante,, Carlos Vergara; Lic. No.: GE2724 23041 AVENIDA DE LA CARLOTA, SUITE 350      LAGUNA HILLS, CA 92653
Engineer Fuller,, Stanley Norman; Lic. No.: C67324 4540 DIRHAM CT      HILLIARD, OH 43026

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/21/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 2/24/2025 Approved DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 2/24/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 3/21/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 3/24/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Grading 5/5/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 5/5/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Grading 4/28/2026 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/28/2026 Partial Inspection EDWIN GREGORYONA
Pre-Inspection 4/28/2026 Approved EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 6/3/2026 Partial Approval EDWIN GREGORYONA