20322 W MOBILE ST 91306
Certificate Information: 20322 W MOBILE ST 91306
- Application / Permit
- 24016-20000-00648
- Plan Check / Job No.
- B24VN00261
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/22/2024
- Issuing Office
- Current Status
- CofO Issued on 4/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 1/11/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 5/15/2024 | ALEC MOUSAKHANIAN |
| Issued | 5/22/2024 | APPLICANT |
| CofO in Progress | 3/25/2025 | ALEXANDER HANDY |
| CofO in Progress | 3/25/2025 | ALEXANDER HANDY |
| CofO in Progress | 3/25/2025 | ALEXANDER HANDY |
| Permit Finaled | 4/28/2025 | JOHN JANSON |
| CofO Issued | 4/28/2025 | JOHN JANSON |
| Permit Finaled | 4/28/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/23/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/23/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/29/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/23/2024 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 8/23/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 9/3/2024 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 9/12/2024 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/4/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 10/4/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/15/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 10/15/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/21/2024 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 10/21/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/24/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 10/24/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/30/2024 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 10/31/2024 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 11/5/2024 | Corrections Issued | JEFFREY HARTLINE |
| Drywall Nailing | 11/13/2024 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/27/2024 | Approved | ALEXANDER HANDY |
| Final | 3/10/2025 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/10/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/18/2025 | Approved | ALEXANDER HANDY |
| Final | 3/18/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Final | 3/18/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/18/2025 | Approved | ALEXANDER HANDY |
| Final | 3/25/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Service/Power Release | 3/25/2025 | Approved | ALEXANDER HANDY |