13933 W VALERIO ST 91405
Certificate Information: 13933 W VALERIO ST 91405
- Application / Permit
- 24016-20000-00575
- Plan Check / Job No.
- B24VN00236
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/26/2024
- Issuing Office
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2024 | ALFRED RAMIREZ |
| Corrections Issued | 1/11/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 6/18/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 6/21/2024 | ISIS ARGUETA |
| Plan Check Approved | 6/25/2024 | ISIS ARGUETA |
| Issued | 6/26/2024 | APPLICANT |
| CofO in Progress | 1/31/2025 | VINCENT HANLEY |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
| CofO Issued | 2/6/2025 | RUBEN SALAS |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/6/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/6/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 5/29/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 8/19/2024 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/21/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/21/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 8/21/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/22/2024 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/22/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 8/22/2024 | Partial Approval | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 8/22/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/26/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/26/2024 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 8/26/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/9/2024 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 10/9/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 10/9/2024 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/15/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/15/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 10/15/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/15/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/18/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 10/18/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/18/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/23/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/23/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/23/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/28/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/28/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/28/2024 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 10/28/2024 | Approved | VINCENT HANLEY |
| Insulation | 10/29/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 11/1/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 11/6/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/6/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 11/6/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/15/2025 | Approved | VINCENT HANLEY |
| Final | 1/15/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 1/15/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/15/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/15/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/15/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 1/15/2025 | Approved | VINCENT HANLEY |
| Final | 1/31/2025 | OK to Issue CofO | VINCENT HANLEY |