1111 S FIGUEROA ST 90015
Certificate Information: 1111 S FIGUEROA ST 90015
- Application / Permit
- 24016-20000-00475
- Plan Check / Job No.
- B24VN00186
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Sports Arena (unlimited seating capacity)
- Work Description
- ** ePlan ** CRYPTO.COM ARENA PHASE 7 - 2024, UPGRADING OF CONCOURSE FINISHES AND RESTROOMS IN MAIN CONCOURSE, REMOVE (E) RAMPS, BUILD (N) PLATFORM FOR (N) WHEELCHAIR LIFT.
- Permit Issued
- Issued on 5/15/2024
- Issuing Office
- Current Status
- Permit Finaled on 11/25/2024
Permit Application Status History
| Submitted | 1/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | JOHNNY WU |
| Assigned to Zoning Architect | 1/18/2024 | JOHNNY WU |
| Corrections Issued | 2/2/2024 | JOHNNY WU |
| Quality Review Completed | 2/6/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 3/19/2024 | JOHNNY WU |
| Applicant returned to address corrections | 4/18/2024 | JOHNNY WU |
| Plan Check Approved | 5/10/2024 | JOHNNY WU |
| Issued | 5/15/2024 | APPLICANT |
| Permit Finaled | 11/20/2024 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 2/21/2024 | JOHNNY WU |
| Specific Plan | Cleared | 2/21/2024 | SOPHIA KIM |
| ZI | Cleared | 2/21/2024 | SOPHIA KIM |
| DAS Clearance | Cleared | 3/13/2024 | Rodolfo Arias |
| Zoning Plan Check | Cleared | 3/19/2024 | Rodolfo Arias |
| Fire Marshal Fire Life Safety | Cleared | 5/7/2024 | MENOA AGHAJANI |
| Green Code | Cleared | 5/8/2024 | MICHAEL AYERS |
Contact Information
| Architect | Szupinski,, Jan Tadeusz; Lic. No.: C13021 | 729 TENTH STREET SANTA MONICA, CA 90402 |
| Contractor | Pcl Construction Services Inc; Lic. No.: 474555-B | , |
| Engineer | Towers,, Kevin; Lic. No.: S6625 | 6121 IROQUOIS RD WESTMINSTER, CA 92683 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/31/2024 | Approved | DARRYL ARNOLD |
| Insulation | 6/1/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 6/1/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 6/3/2024 | Approved | RAFAEL CORTES |
| Insulation | 6/3/2024 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 6/3/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 6/4/2024 | Off-Hour Fees Due | |
| Drywall Nailing | 6/4/2024 | Partial Approval | RONALD JIMENEZ |
| Insulation | 6/4/2024 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 6/4/2024 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 6/4/2024 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 6/6/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 6/7/2024 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 6/19/2024 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 6/21/2024 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 6/28/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 7/6/2024 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 7/9/2024 | Partial Approval | ADAM BURGESS |
| Final | 7/10/2024 | Partial Approval | LUIS CCAMACHO |
| Green Building Final | 7/10/2024 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 7/10/2024 | Approved | LUIS CCAMACHO |
| Final | 7/12/2024 | No Access for Inspection | JEROME BLACKWOOD |
| Final | 7/17/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 7/20/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Light Gage Steel Frame | 7/22/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 7/24/2024 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 7/25/2024 | Approved | DARRYL ARNOLD |
| Insulation | 7/25/2024 | Approved | DARRYL ARNOLD |
| Light Gage Steel Frame | 7/25/2024 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 7/26/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 8/17/2024 | Approved | DARRYL ARNOLD |
| Light Gage Steel Frame | 8/17/2024 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 8/17/2024 | Partial Approval | DARRYL ARNOLD |
| Light Gage Steel Frame | 9/3/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 9/4/2024 | Partial Inspection | LUIS CCAMACHO |
| Drywall Nailing | 9/5/2024 | Partial Approval | LUIS CCAMACHO |
| Insulation | 9/6/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 9/9/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 9/11/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 9/18/2024 | Partial Approval | MARTIN TAVITIAN |
| Insulation | 9/18/2024 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 9/18/2024 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 9/19/2024 | No Access for Inspection | DARRYL ARNOLD |
| Final | 10/15/2024 | Corrections Issued | RONALD JIMENEZ |
| Final | 11/1/2024 | Partial Approval | PAUL BAZERKANIAN |
| Final | 11/20/2024 | Permit Finaled | PAUL BAZERKANIAN |