636 E 84TH ST 90001

Certificate Information: 636 E 84TH ST 90001

Application / Permit
24016-20000-00418
Plan Check / Job No.
B24VN00149
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF EXISTING SFD. REFRAME FOR NEW GABLE ROOF. AUTOMATIC SPRINKLER SYSTEM REQUIRED. CREATE NEW BEDROOM, BATH, CLOSET. REMODEL EX. BEDROOMS, KITCHEN, BATHROOMS, REPAIR EXISTING DAMAGED EXTERIOR WALLS. REPLACE WINDOWS AND DOORS PER PLANS. NEW COVERED PATIO ADDITION. WORK PER WFPP.
Permit Issued
Issued on 3/25/2024
Issuing Office
Current Status
CofO Issued on 10/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2024 APPLICANT
Assigned to Plan Check Engineer 1/12/2024 ROSENDO MEDINA
Corrections Issued 1/12/2024 ROSENDO MEDINA
Applicant returned to address corrections 2/18/2024 ROSENDO MEDINA
Plan Check Approved 2/20/2024 ROSENDO MEDINA
Issued 3/25/2024 APPLICANT
CofO in Progress 10/8/2025 MICHAEL LEWIS
Permit Finaled 10/9/2025 DEROLD HAUFF
Permit Finaled 10/9/2025 DEROLD HAUFF
CofO Issued 10/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/22/2024 ANTHONY TRAN
Eng Process Fee Ord 176,300 Cleared 1/24/2024 ANTHONY TRAN
Sewer availability Cleared 1/24/2024 ANTHONY TRAN

Contact Information

Contractor Ntc Development; Lic. No.: 897288-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 7/26/2024 Corrections Issued DAVID FEILER
PLUMBING-Rough 7/26/2024 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 10/16/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 10/16/2024 Not Ready for Inspection MICHAEL LEWIS
Deputy Drilled-In Anchors 11/18/2024 Conditional Approval MICHAEL LEWIS
PLUMBING-Rough 11/18/2024 Partial Approval MICHAEL LEWIS
Wood Frame 11/18/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Partial Approval MICHAEL LEWIS
Insulation 12/13/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 12/23/2024 Not Ready for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 5/21/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 5/21/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 5/21/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 5/21/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 5/23/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 5/23/2025 Approved LUIS CASTRO
HVAC-Rough 5/23/2025 Approved LUIS CASTRO
PLUMBING-Rough 5/23/2025 Approved LUIS CASTRO
Insulation 6/5/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 6/5/2025 Corrections Issued JOHN QUINTANILLA
Drywall Nailing 6/24/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 6/26/2025 Approved ANTHONY RAMOS
Shower Pan 6/26/2025 Approved ANTHONY RAMOS
HVAC-Final 8/27/2025 Partial Approval JOHN QUINTANILLA
PLUMBING-Final 8/27/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 8/27/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 9/2/2025 Approved JOHN QUINTANILLA
Final 9/16/2025 Corrections Issued SABAS ALONSO
Final 9/19/2025 Corrections Issued BRENDAN MORELLI
Final 9/25/2025 OK to Issue CofO JOHN QUINTANILLA