1000 W VIN SCULLY AVE 90012
Certificate Information: 1000 W VIN SCULLY AVE 90012
- Application / Permit
- 24016-10001-22751
- Plan Check / Job No.
- B24LA29094
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (52) Foundation Only
- Work Description
- FOUNDATION ONLY PERMIT FOR 24016-10000-22751 Remodel and addition of Dodger Stadium. Work includes clubhouse improvements and expansion for Left Field and Right Field, improvements to the home and visitors clubhouses. Excavation, removal, replacement of existing and new: slab(s), ramp(s), stair(s), etc. Repair portions of concrete deck at baseline and field level seating. (renovation to adjacent area as necessary).
- Permit Issued
- Issued on 11/13/2024
- Issuing Office
- Current Status
- Permit Finaled on 3/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 11/13/2024 | APPLICANT |
Plan Check Approved | 11/13/2024 | HERNAN ARREOLA |
Issued | 11/13/2024 | APPLICANT |
Permit Finaled | 3/18/2025 | RONALD JIMENEZ |
Permit Application Clearance Information
Excavation more than 5-ft deep | Cleared | 10/28/2024 | CALOSHA APPROVED |
CPC | Cleared | 10/29/2024 | MAYELA VILLA |
Fire Marshal Fire Life Safety | Cleared | 10/29/2024 | MENOA AGHAJANI |
Miscellaneous | Cleared | 10/29/2024 | MAYELA VILLA |
Miscellaneous | Cleared | 10/29/2024 | MAYELA VILLA |
Miscellaneous | Cleared | 10/29/2024 | MAYELA VILLA |
Miscellaneous | Cleared | 10/29/2024 | MAYELA VILLA |
Miscellaneous | Cleared | 10/29/2024 | MAYELA VILLA |
Miscellaneous | Cleared | 10/29/2024 | MAYELA VILLA |
ZA Case | Cleared | 10/29/2024 | MAYELA VILLA |
Zoning Plan Check | Cleared | 10/30/2024 | ERIC ROMERO |
Contact Information
Architect | Quirk,, Thomas Daniel; Lic. No.: C24479 | 42 8TH STREET UNIT 4208 CHARLESTOWN, MA 02129 |
Contractor | Bernards Builders Inc; Lic. No.: 977134-B | 555 FIRST STREET SAN FERNANDO, CA 91340 |
Engineer | Lay,, Chi-Hung Garry; Lic. No.: GE508 | 885 S ORANGE GROVE BLVD APT 39 PASADENA, CA 91105 |
Engineer | Wilkerson,, Ryan Lee; Lic. No.: S4728 | 20734 SARDINIA WAY PORTER RANCH, CA 91326 |
Inspector Information
JULIAN CAPUCETTI, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 11/18/2024 | Partial Inspection | RAMAZANALI ALMASI |
Excavation/Setback/Form/Re-Bar | 12/2/2024 | Partial Inspection | RAMAZANALI ALMASI |
Footing/Foundation/Slab | 12/2/2024 | Conditional Approval | DARRYL ARNOLD |
Footing/Foundation/Slab | 12/3/2024 | Partial Approval | RAMAZANALI ALMASI |
Reinforced Concrete Frame | 12/3/2024 | Off-Hour Fees Due | |
Reinforced Concrete Frame | 12/3/2024 | Partial Approval | JEROME BLACKWOOD |
Footing/Foundation/Slab | 12/4/2024 | Partial Approval | RAMAZANALI ALMASI |
Deputy Drilled-In Anchors | 12/5/2024 | Conditional Approval | RAMAZANALI ALMASI |
Deputy Reinf. Concrete | 12/5/2024 | Conditional Approval | RAMAZANALI ALMASI |
Deputy Steel/Welding | 12/5/2024 | Conditional Approval | RAMAZANALI ALMASI |
Footing/Foundation/Slab | 12/5/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
Footing/Foundation/Slab | 12/6/2024 | Partial Approval | LUIS CCAMACHO |
Footing/Foundation/Slab | 12/7/2024 | Partial Approval | RONALD JIMENEZ |
Footing/Foundation/Slab | 12/9/2024 | Partial Approval | ALFREDO LOPEZ |
Footing/Foundation/Slab | 12/10/2024 | Partial Approval | RAMAZANALI ALMASI |
Deputy Reinf. Concrete | 12/11/2024 | Conditional Approval | RAMAZANALI ALMASI |
Footing/Foundation/Slab | 12/11/2024 | Conditional Approval | DARRYL ARNOLD |
Reinforced Concrete Frame | 12/11/2024 | Conditional Approval | DARRYL ARNOLD |
Excavation/Setback/Form/Re-Bar | 12/12/2024 | Partial Approval | JEROME BLACKWOOD |
Deputy Reinf. Concrete | 1/16/2025 | Conditional Approval | RAMAZANALI ALMASI |
Excavation/Setback/Form/Re-Bar | 2/24/2025 | Approved | DARRYL ARNOLD |
Final | 3/17/2025 | Conditional Approval | RONALD JIMENEZ |
Smoke Detectors | 3/17/2025 | Approved | RONALD JIMENEZ |
Final | 3/18/2025 | Permit Finaled | RONALD JIMENEZ |