425 E 112TH ST 90061

Certificate Information: 425 E 112TH ST 90061

Application / Permit
24016-10001-09096
Plan Check / Job No.
B24LA16765
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Supplemental permit to 24016-10000-09096 to enlarge addition for new bathroom.
Permit Issued
Issued on 8/29/2024
Issuing Office
Current Status
Permit Finaled on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/9/2024 ADAM HEGAZI
Corrections Issued 8/9/2024 ADAM HEGAZI
Plan Check Approved 8/28/2024 ADAM HEGAZI
Issued 8/29/2024 APPLICANT
Permit Finaled 7/21/2025 JOHN KLARIN

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/13/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/14/2024 DAVID LOPEZ

Contact Information

Architect Yoo,, Won Warren; Lic. No.: C37091 2540 EVELYN STREET      MONTROSE, CA 91020
Contractor Choe Craig; Lic. No.: 867838-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/13/2024 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 9/18/2024 Corrections Issued BARRY HACHE
PLUMBING-Rough 9/18/2024 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 11/5/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 11/5/2024 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 11/12/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 12/13/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 12/13/2024 Approved JOSEPH MCGARRY
Wood Frame 12/20/2024 Corrections Issued ANTHONY EGSON
Deputy Drilled-In Anchors 1/14/2025 Conditional Approval ANTHONY EGSON
Wood Frame 4/28/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 6/2/2025 Corrections Issued JOHN KLARIN
Drywall Nailing 6/3/2025 Approved JOHN KLARIN
Interior/Exterior Lathing 6/3/2025 Approved JOHN KLARIN
ELECTRICAL-Final 7/11/2025 Corrections Issued ANTHONY EGSON
HVAC-Final 7/11/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 7/11/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 7/15/2025 Approved JOHN KLARIN
HVAC-Final 7/15/2025 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/21/2025 Approved JOHN KLARIN
Final 7/21/2025 Permit Finaled JOHN KLARIN
Green Building Final 7/21/2025 Approved JOHN KLARIN
Green Building Rough 7/21/2025 Approved JOHN KLARIN
Smoke Detectors 7/21/2025 Approved JOHN KLARIN