3434 N FARNSWORTH AVE 90032

Certificate Information: 3434 N FARNSWORTH AVE 90032

Application / Permit
24016-10000-40453
Plan Check / Job No.
B24LA37783
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF CANTILEVER COVER PATIO AT FRONT OF (E) SFD AND CONCRETE PATIO AT ENTRY WITH STAIRS.
Permit Issued
Issued on 3/28/2025
Issuing Office
Metro
Current Status
CofO Issued on 12/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2024 APPLICANT
Assigned to Plan Check Engineer 12/27/2024 NEHEMIAS RAMOS
Corrections Issued 12/27/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 2/6/2025 JOSE VELAZQUEZ
Applicant returned to address corrections 3/14/2025 SAMUEL GONZALEZ
Plan Check Approved 3/28/2025 MINA HABILI
Issued 3/28/2025 APPLICANT
CofO in Progress 12/2/2025 LILIANA PORTILLO
Permit Finaled 12/3/2025 DEROLD HAUFF
CofO Issued 12/3/2025 DEROLD HAUFF
Permit Finaled 12/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/6/2025 CHRISTINA BRACO
Grading Pre-Inspection Cleared 2/6/2025 JOSE VELAZQUEZ
Roof/Waste drainage to street Cleared 2/6/2025 CHRISTINA BRACO
Watercourse Cleared 3/27/2025 TERRY PHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Ficinski,, Marek; Lic. No.: S3534 4850 N LANTE ST      BALDWIN PARK, CA 91706

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/15/2025 Corrections Issued LILIANA PORTILLO
Wood Frame 5/15/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 6/5/2025 Not Ready for Inspection BRENDAN MORELLI
Wood Frame 6/5/2025 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 6/16/2025 Approved LILIANA PORTILLO
Insulation 7/8/2025 Approved LILIANA PORTILLO
Wood Frame 7/8/2025 Approved LILIANA PORTILLO
Drywall Nailing 7/15/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Not Ready LILIANA PORTILLO
Final 9/16/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 9/16/2025 Approved LILIANA PORTILLO
Green Building Final 9/16/2025 Approved LILIANA PORTILLO
Green Building Rough 9/16/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 9/16/2025 Corrections Issued LILIANA PORTILLO
Wood Frame 9/16/2025 Approved LILIANA PORTILLO
Final 11/13/2025 No Access for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 11/13/2025 No Access for Inspection LILIANA PORTILLO
Final 11/25/2025 OK to Issue CofO LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 11/25/2025 Approved LILIANA PORTILLO