951 S WILTON PL 101 90019
Certificate Information: 951 S WILTON PL 101 90019
- Application / Permit
- 24016-10000-40448
- Plan Check / Job No.
- B24LA37777
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. convert 350 sf recroom to ADU in an existing apartment
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Current Status
- CofO Corrected on 7/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2025 | APPLICANT |
| Assigned to Zoning Architect | 1/9/2025 | AMIR NAKHLA |
| Assigned to Plan Check Engineer | 1/16/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 1/23/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/4/2025 | PRANITA SHAH |
| Plan Check Approved | 2/26/2025 | ARSALAN SHABESTARI |
| Issued | 2/27/2025 | APPLICANT |
| CofO in Progress | 5/27/2025 | MARTIN TAVITIAN |
| CofO Issued-Status Void | 5/27/2025 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 5/27/2025 | ERNESTO CORRAL |
| Re-Activate Permit | 7/15/2025 | ADAM BURGESS |
| CofO Corrected | 7/15/2025 | ADAM BURGESS |
| Permit Finaled | 7/15/2025 | ADAM BURGESS |
Permit Application Clearance Information
| HPOZ | Cleared | 1/21/2025 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 1/21/2025 | MICAELA TORRES-GIL |
| DAS Clearance | Cleared | 1/22/2025 | Rosendo Medina |
| Zoning Plan Check | Cleared | 1/22/2025 | Rosendo Medina |
| Tenant Habitability Plan | Cleared | 1/24/2025 | RICARDO BOHORQUEZ |
| Sewer availability | Cleared | 2/1/2025 | TAL SHEMEN |
| Address approval | Cleared | 2/7/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2025 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2025 | Approved | MARTIN TAVITIAN |
| Final | 5/5/2025 | Conditional Approval | MARTIN TAVITIAN |
| Reinforced Concrete Frame | 5/5/2025 | Approved | MARTIN TAVITIAN |
| Smoke Detectors | 5/5/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 5/5/2025 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 5/7/2025 | Approved | MARTIN TAVITIAN |
| Final | 5/7/2025 | OK to Issue CofO | MARTIN TAVITIAN |